144 S HARVARD BLVD 90004

Certificate Information: 144 S HARVARD BLVD 90004

Application / Permit
21014-10000-01910
Plan Check / Job No.
B21LA07156
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION [18'-0" X 23'-0"] TO REAR OF SFD FOR NEW 3RD BEDROOM, NEW BATHROOM, AND WALK IN CLOSET. RELOCATING KITCHEN.
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
CofO Issued on 9/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 FARSHAD ALIMOHAMADI
Corrections Issued 4/21/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 5/12/2021 JESSE JIMENEZ
Building Plans Picked Up 5/13/2021 APPLICANT
Plan Check Approved 6/9/2021 FARSHAD ALIMOHAMADI
Issued 6/17/2021 APPLICANT
CofO in Progress 9/15/2021 CHRIS CHRISTENSEN
Permit Finaled 9/25/2021 DEROLD HAUFF
CofO Issued 9/25/2021 DEROLD HAUFF
Permit Finaled 9/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/17/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 5/17/2021 STEVE MELGAR
Sewer availability Cleared 5/17/2021 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 6/29/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/29/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/29/2021 Partial Approval CHRIS CHRISTENSEN
Pre-Inspection 6/29/2021 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 7/1/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/2/2021 Approved BENEVA JACKSON
Drywall Nailing 7/14/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/29/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 7/29/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/29/2021 Approved CHRIS CHRISTENSEN
Wood Frame 7/29/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/30/2021 Approved ARTHUR SARGSYAN
Insulation 7/30/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 8/2/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/3/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/14/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 9/14/2021 Approved CHRIS CHRISTENSEN
Final 9/14/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 9/14/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 9/14/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 9/14/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/14/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 9/14/2021 Approved CHRIS CHRISTENSEN