13952 W CARL ST 91331
Certificate Information: 13952 W CARL ST 91331
- Application / Permit
- 21014-10000-01908
- Plan Check / Job No.
- B21LA07145
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW BEDROOM ADDITION AND SFD (15'-5" X 11'-10") WITH SQUARE FOOTAGE OF 182.43 SF AND BUILD A NEW LAUNDRY AREA NEXT TO EXISTING GARAGE LAUNDRY DIMENSIONS ARE (11''-10" X 6'-2") WITH SQUARE FOOTAGE = 72.97 SF.
- Permit Issued
- Issued on 8/20/2021
- Issuing Office
- Current Status
- CofO Issued on 7/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 4/21/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 6/15/2021 | ZAW HAN |
| Plan Check Approved | 8/11/2021 | ZAW HAN |
| Issued | 8/20/2021 | APPLICANT |
| Building Plans Picked Up | 8/24/2021 | APPLICANT |
| CofO in Progress | 7/8/2022 | MICHEL ABAJAN |
| Permit Finaled | 7/12/2022 | RONALD MYRICK |
| CofO Issued | 7/12/2022 | RONALD MYRICK |
| Permit Finaled | 7/12/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/24/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/26/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/5/2022 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/6/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 4/6/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 4/6/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/2/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/5/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/5/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 5/5/2022 | Approved | MICHEL ABAJAN |
| Insulation | 5/9/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/11/2022 | Approved | MICHEL ABAJAN |
| Final | 6/21/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/21/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/21/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/8/2022 | Approved | MICHEL ABAJAN |
| Final | 7/8/2022 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 7/8/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/8/2022 | Approved | MICHEL ABAJAN |