1172 S MASSELIN AVE 90019

Certificate Information: 1172 S MASSELIN AVE 90019

Application / Permit
21014-10000-01892
Plan Check / Job No.
B21LA07096
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
HOUSE REMODEL AND ADDITION 2 OF 2
Permit Issued
Issued on 7/15/2021
Issuing Office
Current Status
CofO Issued on 2/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 SERGIO GUTIERREZ
Corrections Issued 5/4/2021 SERGIO GUTIERREZ
Quality Review Completed 5/6/2021 FARUK SEZER
Building Plans Picked Up 5/10/2021 APPLICANT
Plan Check Approved 7/15/2021 SERGIO GUTIERREZ
Issued 7/15/2021 APPLICANT
CofO in Progress 2/1/2023 JOSE AVILA
Permit Finaled 2/7/2023 DEROLD HAUFF
CofO Issued 2/7/2023 DEROLD HAUFF
Permit Finaled 2/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/11/2021 WALLIE JONG
Sewer availability Cleared 5/11/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/13/2021 WALLIE JONG
Hydrant and Access approval Cleared 6/22/2021 KURT CORRAL

Contact Information

Contractor N A N D C O Llc; Lic. No.: 1044615-B 4836 FULTON AVE      SHERMAN OAKS, CA 91423
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Barrier 7/27/2021 Not Ready for Inspection JOAQUIN GREENOUGH
METHANE-Subgrade 7/27/2021 Corrections Issued JOAQUIN GREENOUGH
Gas Test 8/24/2021 Approved JESUS PINEDA
PLUMBING-Rough 8/24/2021 Partial Approval JESUS PINEDA
Pre-Inspection 8/24/2021 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Not Ready for Inspection STUART CHAPMAN
Deputy Wood Construction 10/18/2021 No Access for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/19/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 11/9/2021 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 2/11/2022 Corrections Issued JOSE AVILA
HVAC-Rough 2/11/2022 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 2/11/2022 Approved JOSE AVILA
PLUMBING-Rough 2/11/2022 Corrections Issued JOSE AVILA
Shower Pan 2/11/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 2/17/2022 Partial Approval JOSE AVILA
ELECTRICAL-Rough 2/17/2022 Approved JOSE AVILA
Green Building Rough 2/17/2022 Approved JOSE AVILA
HVAC-Rough 2/17/2022 Partial Approval JOSE AVILA
Interior/Exterior Lathing 2/17/2022 Approved JOSE AVILA
METHANE-Rough 2/17/2022 Approved JOSE AVILA
Wood Frame 2/17/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 3/3/2022 Approved JOSE AVILA
Insulation 3/3/2022 Approved JOSE AVILA
Interior/Exterior Lathing 3/3/2022 Approved JOSE AVILA
Drywall Nailing 3/11/2022 Corrections Issued JOSE AVILA
Gas Test 6/2/2022 Approved JOSE AVILA
HVAC-Final 6/2/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 6/2/2022 Corrections Issued JOSE AVILA
Service/Power Release 6/2/2022 Not Ready for Inspection JOSE AVILA
Service/Power Release 6/10/2022 Partial Approval JOSE AVILA
Service/Power Release 7/26/2022 Approved JOSE AVILA
ELECTRICAL-Final 8/1/2022 Approved JOSE AVILA
Final 8/1/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 8/1/2022 Approved JOSE AVILA
Green Building Final 8/1/2022 Corrections Issued JOSE AVILA
HVAC-Final 8/1/2022 Corrections Issued JOSE AVILA
METHANE-Barrier 8/1/2022 Approved JOSE AVILA
METHANE-Subgrade 8/1/2022 Approved JOSE AVILA
PLUMBING-Final 8/1/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 8/1/2022 Approved JOSE AVILA
ELECTRICAL-Final 9/28/2022 Approved JOSE AVILA
Final 9/28/2022 Corrections Issued JOSE AVILA
Green Building Final 9/28/2022 Corrections Issued JOSE AVILA
HVAC-Final 9/28/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 9/28/2022 Corrections Issued JOSE AVILA
Service/Power Release 9/28/2022 Approved JOSE AVILA
ELECTRICAL-Final 10/19/2022 Approved JOSE AVILA
Final 10/19/2022 Corrections Issued JOSE AVILA
Green Building Final 10/19/2022 Approved JOSE AVILA
HVAC-Final 10/19/2022 Conditional Approval JOSE AVILA
PLUMBING-Final 10/19/2022 Corrections Issued JOSE AVILA
HVAC-Final 11/23/2022 Approved BRENDAN MORELLI
PLUMBING-Final 11/23/2022 Approved BRENDAN MORELLI
Final 1/31/2023 OK to Issue CofO JOSE AVILA