552 E WESTMINSTER AVE 90291

Certificate Information: 552 E WESTMINSTER AVE 90291

Application / Permit
21014-10000-01875
Plan Check / Job No.
B21LA07042
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. new detached adu
Permit Issued
Issued on 5/4/2022
Issuing Office
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 ARSALAN SHABESTARI
Corrections Issued 5/29/2021 ARSALAN SHABESTARI
Quality Review Completed 6/8/2021 MICHAEL PEREZ
Applicant returned to address corrections 8/9/2021 ARSALAN SHABESTARI
Applicant returned to address corrections 8/31/2021 ARSALAN SHABESTARI
Plan Check Approved 9/20/2021 ARSALAN SHABESTARI
Issued 5/4/2022 APPLICANT
CofO in Progress 4/20/2023 EVAN COOPER
Permit Finaled 5/2/2023 DANIEL ORRANTE
CofO Issued 5/2/2023 DANIEL ORRANTE
Permit Finaled 5/2/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 6/16/2021 WALTER RAMIREZ
Construction within easement Cleared 6/16/2021 WALTER RAMIREZ
Address approval Cleared 6/22/2021 HISASHI KOBAYAKAWA
Specific Plan Cleared 6/22/2021 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 6/29/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/29/2021 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 7/19/2021 ANTHONY MAINEZ
Miscellaneous Cleared 8/17/2021 IRA BROWN
Specific Plan Cleared 8/18/2021 PEDRO AYALA
Specific Plan Cleared 8/19/2021 IRA BROWN
Miscellaneous Cleared 9/8/2021 MARITZA PRZEKOP
Miscellaneous Cleared 9/8/2021 MARITZA PRZEKOP
Miscellaneous Cleared 9/8/2021 MARITZA PRZEKOP
ZA Case Cleared 9/8/2021 MARITZA PRZEKOP

Contact Information

Contractor A - 1 Construction; Lic. No.: 629700-B 10650 OVERMAN AVENUE      CHATSWORTH, CA 91311

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/11/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 7/11/2022 Not Ready for Inspection DAVID FEILER
METHANE-Barrier 7/11/2022 Approved DAVID FEILER
METHANE-Subgrade 7/11/2022 Approved DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/15/2022 Approved DAVID FEILER
Footing/Foundation/Slab 7/15/2022 Partial Approval DAVID FEILER
Underground Mechanical 7/21/2022 Approved DAVID FEILER
Deputy Steel/Welding 8/8/2022 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 8/8/2022 Approved STEPHANIE SWANSON
Deputy Steel/Welding 8/23/2022 Approved MICHAEL PELHAM
Deputy Wood Construction 9/16/2022 Conditional Approval DAVID FEILER
Deputy Drilled-In Anchors 9/19/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval DAVID FEILER
Gas Test 10/6/2022 Partial Inspection DAVID FEILER
PLUMBING-Rough 10/6/2022 Approved DAVID FEILER
Structural Steel Frame 10/6/2022 Not Ready for Inspection DAVID FEILER
Wood Frame 10/6/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 10/13/2022 Corrections Issued DAVID FEILER
Deputy Wood Construction 10/19/2022 No Access for Inspection DAVID FEILER
BUILDING-Rough-Frame 10/20/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 10/20/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/20/2022 Approved DAVID FEILER
Green Building Rough 10/20/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 10/20/2022 Not Ready for Inspection DAVID FEILER
METHANE-Rough 10/20/2022 Approved DAVID FEILER
Structural Steel Frame 10/20/2022 Approved DAVID FEILER
Verify Sprinkler Sign Off 10/20/2022 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 10/24/2022 Partial Approval DAVID FEILER
Green Building Rough 10/24/2022 Approved DAVID FEILER
Interior/Exterior Lathing 10/24/2022 Not Ready for Inspection DAVID FEILER
Insulation 11/1/2022 Not Ready for Inspection DAVID FEILER
Shower Pan 11/1/2022 Not Ready for Inspection DAVID FEILER
Insulation 11/16/2022 Corrections Issued DAVID FEILER
Shower Pan 11/16/2022 Corrections Issued DAVID FEILER
Insulation 11/18/2022 Approved DAVID FEILER
Interior/Exterior Lathing 11/18/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 11/18/2022 Not Ready for Inspection DAVID FEILER
Shower Pan 11/18/2022 Not Ready for Inspection DAVID FEILER
Drywall Nailing 12/6/2022 Approved EVAN COOPER
Interior/Exterior Lathing 12/6/2022 Approved EVAN COOPER
Special/Order Compliance 12/6/2022 Partial Inspection JEREMY TODD
Service/Power Release 2/6/2023 Corrections Issued JESUS RODRIGUEZ
Sewer 2/6/2023 Approved JESUS RODRIGUEZ
Deputy Steel/Welding 2/8/2023 Conditional Approval EVAN COOPER
Service/Power Release 2/9/2023 Approved JESUS RODRIGUEZ
Shower Pan 2/14/2023 Approved JESUS RODRIGUEZ
Structural Steel Frame 2/14/2023 Not Ready for Inspection JESUS RODRIGUEZ
Gas Test 2/28/2023 Partial Approval EVAN COOPER
Structural Steel Frame 2/28/2023 Not Ready for Inspection EVAN COOPER
Gas Test 3/1/2023 Not Ready for Inspection EVAN COOPER
Gas Test 3/2/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 4/17/2023 Approved EVAN COOPER
ELECTRICAL-Final 4/17/2023 Approved EVAN COOPER
Final 4/17/2023 Corrections Issued EVAN COOPER
Green Building Final 4/17/2023 Approved EVAN COOPER
HVAC-Final 4/17/2023 Approved EVAN COOPER
PLUMBING-Final 4/17/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/17/2023 SGSOV Approved EVAN COOPER
Smoke Detectors 4/17/2023 Approved EVAN COOPER
Verify Sprinkler Sign Off 4/17/2023 Approved EVAN COOPER
Final 4/20/2023 OK to Issue CofO EVAN COOPER