416 N EZRA ST 90063
Certificate Information: 416 N EZRA ST 90063
- Application / Permit
- 21014-10000-01865
- Plan Check / Job No.
- B21LA07000
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ONE CAR GARAGE TO BEDROOM, CONVERT PORTION OF (E) DINING TO BATHROOM AND ADD ATTACHED CARPORT. "COMPLY WITH DEPARTMENT ORDER effective date 02/26/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 4/19/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 10/21/2021 | JOSEPH RAFOLS |
| Issued | 11/1/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| CofO in Progress | 10/27/2023 | HAGOP BADOSSIAN |
| Permit Finaled | 12/19/2023 | DANIEL SANCHEZ |
| Permit Finaled | 12/19/2023 | DANIEL SANCHEZ |
| CofO Issued | 12/19/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/5/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 5/10/2021 | KIRK LINKLATER |
| Construction near power lines | Cleared | 7/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/7/2021 | Corrections Issued | JUAN ESCOTO DELGADO |
| Footing/Foundation/Slab | 2/10/2022 | Corrections Issued | JUAN ESCOTO DELGADO |
| Footing/Foundation/Slab | 2/24/2022 | Partial Approval | JUAN ESCOTO DELGADO |
| Footing/Foundation/Slab | 3/4/2022 | Partial Approval | JUAN ESCOTO DELGADO |
| BUILDING-Rough-Frame | 3/17/2022 | Corrections Issued | JUAN ESCOTO DELGADO |
| Green Building Rough | 3/17/2022 | Approved | JUAN ESCOTO DELGADO |
| Insulation | 3/18/2022 | Partial Approval | JUAN ESCOTO DELGADO |
| BUILDING-Rough-Frame | 4/29/2022 | Partial Approval | JUAN ESCOTO DELGADO |
| ELECTRICAL-Rough | 8/3/2022 | Approved | JUAN ESCOTO DELGADO |
| Wood Frame | 8/3/2022 | Approved | JUAN ESCOTO DELGADO |
| ELECTRICAL-Rough | 8/8/2022 | Approved | JUAN ESCOTO DELGADO |
| Wood Frame | 8/8/2022 | Approved | JUAN ESCOTO DELGADO |
| Insulation | 8/9/2022 | Approved | JUAN ESCOTO DELGADO |
| Drywall Nailing | 9/13/2022 | Approved | JUAN ESCOTO DELGADO |
| Interior/Exterior Lathing | 9/13/2022 | Approved | JUAN ESCOTO DELGADO |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | RAUL VASQUEZ |
| Final | 8/16/2023 | Not Ready for Inspection | RAUL VASQUEZ |
| Footing/Foundation/Slab | 8/16/2023 | Not Ready for Inspection | RAUL VASQUEZ |
| Green Building Final | 8/16/2023 | Not Ready for Inspection | RAUL VASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 8/16/2023 | SGSOV Not Ready | RAUL VASQUEZ |
| Smoke Detectors | 8/16/2023 | Not Ready for Inspection | RAUL VASQUEZ |
| Deputy Drilled-In Anchors | 9/14/2023 | Approved | PEDRO SIERRA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Approved | PEDRO SIERRA |
| BUILDING-Rough-Frame | 9/27/2023 | Approved | RAUL VASQUEZ |
| Final | 9/27/2023 | Conditional Approval | RAUL VASQUEZ |
| Footing/Foundation/Slab | 9/27/2023 | Approved | RAUL VASQUEZ |
| Green Building Final | 9/27/2023 | Approved | RAUL VASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Approved | RAUL VASQUEZ |
| Smoke Detectors | 9/27/2023 | Approved | RAUL VASQUEZ |
| Final | 10/18/2023 | Conditional Approval | PEDRO SIERRA |