7706 W SUMMITROSE ST 91042

Certificate Information: 7706 W SUMMITROSE ST 91042

Application / Permit
21014-10000-01863
Plan Check / Job No.
B21LA06998
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND LAUNDRY ROOM TO ACCESSORY DWELLING UNIT WITH ADDITION.
Permit Issued
Issued on 6/15/2021
Issuing Office
Current Status
CofO Issued on 8/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2021 APPLICANT
Assigned to Plan Check Engineer 4/21/2021 FARSHAD ALIMOHAMADI
Corrections Issued 4/22/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 5/30/2021 FARSHAD ALIMOHAMADI
Issued 6/15/2021 APPLICANT
Building Plans Picked Up 6/17/2021 APPLICANT
CofO in Progress 6/15/2022 MATTHEW NELSON
Permit Finaled 8/5/2022 DANIEL ORRANTE
CofO Issued 8/5/2022 DANIEL ORRANTE
Permit Finaled 8/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/26/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/26/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/3/2021 LEE GUILBEAUX
Sewer availability Cleared 5/3/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/3/2021 LEE GUILBEAUX
Grading Pre-Inspection Cleared 5/18/2021 BRIAN MILLER

Contact Information

Contractor Home Upgrade Specialist Inc; Lic. No.: 1031989-C20 733 NORTH LA BREA AVE #200      LOS ANGELES, CA 90038
Engineer Sin,, John P; Lic. No.: C91162 122 N GRAMERCY PL      LOS ANGELES, CA 90004

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/18/2021 Approved MATTHEW NELSON
Footing/Foundation/Slab 10/18/2021 Approved MATTHEW NELSON
Underground Mechanical 10/29/2021 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 12/9/2021 Approved MATTHEW NELSON
PLUMBING-Rough 12/9/2021 Approved MATTHEW NELSON
Wood Frame 12/16/2021 Partial Approval MATTHEW NELSON
Deputy Wood Construction 1/5/2022 Conditional Approval MATTHEW NELSON
HVAC-Rough 1/10/2022 Approved MATTHEW NELSON
Wood Frame 1/28/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/10/2022 Approved MATTHEW NELSON
Green Building Rough 2/25/2022 Approved MATTHEW NELSON
Insulation 2/25/2022 Approved MATTHEW NELSON
Shower Pan 3/4/2022 Approved MATTHEW NELSON
Drywall Nailing 3/9/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 5/5/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 6/3/2022 Corrections Issued MATTHEW NELSON
Gas Test 6/3/2022 Approved MATTHEW NELSON
PLUMBING-Final 6/3/2022 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 6/6/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 6/10/2022 Approved MATTHEW NELSON
HVAC-Final 6/10/2022 Approved MATTHEW NELSON
PLUMBING-Final 6/10/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/15/2022 Approved MATTHEW NELSON
Final 6/15/2022 OK to Issue CofO MATTHEW NELSON
Green Building Final 6/15/2022 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved MATTHEW NELSON
Smoke Detectors 6/15/2022 Approved MATTHEW NELSON