14651 W ALBERS ST 91411
Certificate Information: 14651 W ALBERS ST 91411
- Application / Permit
- 21014-10000-01858
- Plan Check / Job No.
- B21LA06988
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-PLAN: Conversion of Existing detached Garage and Recreation Room to accessory dwelling unit per LAMC 12.22A.33(b)(5)
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 5/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2021 | MONICA RAMIREZ |
| Corrections Issued | 4/20/2021 | MONICA RAMIREZ |
| Plan Check Approved | 6/21/2021 | MONICA RAMIREZ |
| Issued | 1/18/2022 | APPLICANT |
| CofO in Progress | 4/14/2022 | JACK KARGODORIAN |
| Permit Finaled | 5/9/2022 | MICHAEL SMITH |
| CofO Issued | 5/9/2022 | MICHAEL SMITH |
| Permit Finaled | 5/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/22/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 5/29/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/31/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/4/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/22/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 2/22/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 2/22/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/1/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/1/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 3/1/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 3/7/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 3/7/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 3/10/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | JACK KARGODORIAN |
| Final | 4/8/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/8/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 4/8/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 4/8/2022 | Approved | JACK KARGODORIAN |
| Final | 4/14/2022 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 4/14/2022 | Approved | JACK KARGODORIAN |