14651 W ALBERS ST 91411

Certificate Information: 14651 W ALBERS ST 91411

Application / Permit
21014-10000-01858
Plan Check / Job No.
B21LA06988
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: Conversion of Existing detached Garage and Recreation Room to accessory dwelling unit per LAMC 12.22A.33(b)(5)
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 5/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2021 APPLICANT
Assigned to Plan Check Engineer 4/20/2021 MONICA RAMIREZ
Corrections Issued 4/20/2021 MONICA RAMIREZ
Plan Check Approved 6/21/2021 MONICA RAMIREZ
Issued 1/18/2022 APPLICANT
CofO in Progress 4/14/2022 JACK KARGODORIAN
Permit Finaled 5/9/2022 MICHAEL SMITH
CofO Issued 5/9/2022 MICHAEL SMITH
Permit Finaled 5/9/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/22/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/22/2021 ADRIAN CASTRO
Sewer availability Cleared 4/22/2021 ADRIAN CASTRO
Construction near power lines Cleared 5/29/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/31/2022 Approved JACK KARGODORIAN
Footing/Foundation/Slab 2/4/2022 Approved JACK KARGODORIAN
ELECTRICAL-Rough 2/22/2022 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 2/22/2022 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 2/22/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 3/1/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 3/1/2022 Approved JACK KARGODORIAN
Wood Frame 3/1/2022 Partial Approval JACK KARGODORIAN
Insulation 3/7/2022 Approved JACK KARGODORIAN
Wood Frame 3/7/2022 Approved JACK KARGODORIAN
Drywall Nailing 3/10/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 4/8/2022 Approved JACK KARGODORIAN
Final 4/8/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 4/8/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 4/8/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 4/8/2022 Approved JACK KARGODORIAN
Final 4/14/2022 OK to Issue CofO JACK KARGODORIAN