5469 S 7TH AVE 90043
Certificate Information: 5469 S 7TH AVE 90043
- Application / Permit
- 21014-10000-01854
- Plan Check / Job No.
- B21LA06973
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY ADDITION TOWARD REAR OF (E) SFD. INCLUDES INTERIOR REMODEL OF (E) PORTION OF UNIT.
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/21/2021 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
| Plan Check Approved | 7/26/2021 | LAWRENCE QUIRANTE |
| Issued | 7/28/2021 | APPLICANT |
| CofO in Progress | 10/19/2022 | ANTHONY EGSON |
| Permit Finaled | 10/28/2022 | DEROLD HAUFF |
| CofO Issued | 10/28/2022 | DEROLD HAUFF |
| Permit Finaled | 10/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/18/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/20/2021 | No Access for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/21/2021 | Approved | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 10/22/2021 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Approved | ANTHONY EGSON |
| Pre-Inspection | 11/18/2021 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 11/18/2021 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/5/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/5/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 4/5/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 4/5/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 4/5/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/16/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/16/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/16/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/17/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/17/2022 | Approved | ANTHONY EGSON |
| Insulation | 6/6/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/6/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/23/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 7/18/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/1/2022 | Approved | MICHAEL LEWIS |
| Final | 9/20/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 9/20/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/20/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/23/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 9/23/2022 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 9/23/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/26/2022 | Approved | ANTHONY EGSON |
| Final | 9/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 9/26/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/26/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/26/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/27/2022 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 9/27/2022 | No Access for Inspection | ANTHONY EGSON |
| Final | 10/7/2022 | OK to Issue CofO | ANTHONY EGSON |