4818 S COOLIDGE AVE 90230

Certificate Information: 4818 S COOLIDGE AVE 90230

Application / Permit
21014-10000-01798
Plan Check / Job No.
B21LA06733
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU addition. Garage expansion into ADU
Permit Issued
Issued on 8/25/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 CARLOS MONTES
Corrections Issued 4/14/2021 CARLOS MONTES
Applicant returned to address corrections 7/23/2021 CARLOS MONTES
Applicant returned to address corrections 7/27/2021 CARLOS MONTES
Plan Check Approved 8/11/2021 CRYSTEL MAALOUF
Issued 8/25/2021 APPLICANT
CofO in Progress 4/21/2022 DAVID FEILER
Permit Finaled 4/28/2022 DANIEL ORRANTE
CofO Issued 4/28/2022 DANIEL ORRANTE
Permit Finaled 4/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/10/2021 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/6/2021 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 7/6/2021 NIKTA MOUSAVI
Specific Plan Cleared 7/8/2021 EILEEN HUNT
Sewer availability Cleared 7/20/2021 NIKTA MOUSAVI

Contact Information

Architect Smith,, David Jordan; Lic. No.: C20495 788 WESLEYAN BAY      COSTA MESA, CA 92626
Contractor Hamodot Isaac; Lic. No.: 1071940-B 7840 W 81 STREET      PLAYA DEL REY, CA 90293
Engineer Poomiwatracanont,, Roy; Lic. No.: S6384 304 N EL MOLINO ST      ALHAMBRA, CA 91801

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/1/2021 Approved ENRIQUE MIRELES
Wood Frame 10/19/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/26/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 11/16/2021 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 11/16/2021 Corrections Issued KENNETH NAGLE
HVAC-Rough 11/16/2021 Approved KENNETH NAGLE
ELECTRICAL-Rough 11/22/2021 Corrections Issued ENRIQUE MIRELES
Wood Frame 11/22/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 12/6/2021 Approved JOHN KAYON
Interior/Exterior Lathing 12/6/2021 Partial Approval JOHN KAYON
Interior/Exterior Lathing 12/17/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/23/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 12/23/2021 Approved ENRIQUE MIRELES
Insulation 12/23/2021 Not Ready for Inspection ENRIQUE MIRELES
MERV13>=Rough 12/23/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 12/23/2021 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 1/3/2022 Approved EVAN COOPER
Insulation 1/3/2022 Approved EVAN COOPER
Drywall Nailing 1/6/2022 Approved JOHN KAYON
Interior/Exterior Lathing 1/21/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 2/28/2022 Approved RICHARD STEINBACH
Final 2/28/2022 Corrections Issued RICHARD STEINBACH
Green Building Final 2/28/2022 Approved RICHARD STEINBACH
HVAC-Final 2/28/2022 Corrections Issued RICHARD STEINBACH
MERV13>=Final 2/28/2022 Approved RICHARD STEINBACH
PLUMBING-Final 2/28/2022 Approved RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Approved RICHARD STEINBACH
Smoke Detectors 2/28/2022 Corrections Issued RICHARD STEINBACH
Final 3/7/2022 Partial Inspection DAVID FEILER
Smoke Detectors 3/7/2022 Approved DAVID FEILER
Final 4/21/2022 OK to Issue CofO DAVID FEILER
HVAC-Final 4/21/2022 Approved DAVID FEILER
Service/Power Release 4/21/2022 Approved DAVID FEILER