6821 N WYSTONE AVE 91335
Certificate Information: 6821 N WYSTONE AVE 91335
- Application / Permit
- 21014-10000-01797
- Plan Check / Job No.
- B21LA06732
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan* Conversion of detached garage to an accessory dwelling unit per LAMC 12.22 A.33(b)(5)
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 5/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | MONICA RAMIREZ |
| Corrections Issued | 4/30/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 9/7/2021 | MONICA RAMIREZ |
| Plan Check Approved | 9/9/2021 | MONICA RAMIREZ |
| Issued | 9/15/2021 | APPLICANT |
| CofO in Progress | 5/3/2022 | VINCENT HANLEY |
| Permit Finaled | 5/12/2022 | MICHAEL SMITH |
| CofO Issued | 5/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/14/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/30/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | M L Builders And Design; Lic. No.: 953612-B | 10400 GLORIA AVENUE GRANADA HILLS, CA 91344 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/5/2021 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/8/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/13/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 10/13/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 10/13/2021 | Partial Approval | VINCENT HANLEY |
| Underground Mechanical | 10/15/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/25/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/25/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/25/2021 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 10/25/2021 | Approved | VINCENT HANLEY |
| Insulation | 10/25/2021 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 10/25/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/2/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/2/2021 | Approved | VINCENT HANLEY |
| Insulation | 11/2/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/2/2021 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 11/8/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/8/2021 | Partial Approval | JESUS PINEDA |
| Shower Pan | 11/8/2021 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 11/15/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 11/15/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/8/2022 | Approved | VINCENT HANLEY |
| Final | 4/8/2022 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 4/8/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 4/8/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/8/2022 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV No Gas | VINCENT HANLEY |
| Smoke Detectors | 4/8/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/2/2022 | Approved | VINCENT HANLEY |
| Final | 5/2/2022 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 5/2/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/2/2022 | Approved | VINCENT HANLEY |