4257 S MENLO AVE 90037
Certificate Information: 4257 S MENLO AVE 90037
- Application / Permit
- 21014-10000-01783
- Plan Check / Job No.
- B21LA06640
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ADU WITH ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/30/2021
- Issuing Office
- Current Status
- CofO Issued on 7/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2021 | SINA KHOSRAVI |
| Corrections Issued | 4/14/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 7/30/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 8/11/2021 | ZAW HAN |
| Plan Check Approved | 8/17/2021 | ZAW HAN |
| Building Plans Picked Up | 8/19/2021 | APPLICANT |
| Issued | 8/30/2021 | APPLICANT |
| CofO in Progress | 7/25/2024 | SABAS ALONSO |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
| CofO Issued | 7/29/2024 | DEROLD HAUFF |
| Permit Finaled | 7/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 5/12/2021 | TERRI OSBORNE |
| "Q" conditions | Cleared | 7/1/2021 | TERRI OSBORNE |
| Address approval | Cleared | 7/1/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 7/1/2021 | CELINA MORENO |
| Sewer availability | Cleared | 7/1/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2021 | CELINA MORENO |
| Construction near power lines | Cleared | 7/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/8/2021 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 12/8/2021 | Corrections Issued | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 12/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 8/4/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/18/2022 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 11/9/2022 | Corrections Issued | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Partial Approval | RYAN SALAZAR |
| HVAC-Rough | 11/9/2022 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 11/9/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/19/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 12/19/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 12/19/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/19/2022 | Approved | SABAS ALONSO |
| Insulation | 12/19/2022 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 3/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/23/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 3/23/2023 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 3/23/2023 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 4/4/2023 | Approved | SABAS ALONSO |
| Insulation | 4/4/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/4/2023 | Partial Approval | SABAS ALONSO |
| Shower Pan | 4/4/2023 | Partial Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 4/27/2023 | Approved | SABAS ALONSO |
| Shower Pan | 4/27/2023 | Approved | SABAS ALONSO |
| Service/Power Release | 10/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 11/16/2023 | Approved | MICHAEL LEWIS |
| Final | 12/12/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/12/2023 | Approved | SABAS ALONSO |
| HVAC-Final | 12/12/2023 | Approved | SABAS ALONSO |
| PLUMBING-Final | 12/12/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 12/12/2023 | Approved | SABAS ALONSO |
| Final | 7/10/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | SABAS ALONSO |
| Final | 7/19/2024 | Corrections Issued | SABAS ALONSO |
| Final | 7/24/2024 | OK to Issue CofO | SABAS ALONSO |