5107 E STRATFORD ROAD 90042

Certificate Information: 5107 E STRATFORD ROAD 90042

Application / Permit
21014-10000-01771
Plan Check / Job No.
B21LA06606
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Ground floor addition to an (E) detached garage and conversion of entire building into an ADU per ordinance 186,481.
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
CofO Issued on 12/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 HELEN NGUYEN
Corrections Issued 4/22/2021 HELEN NGUYEN
Quality Review Completed 4/28/2021 MICHAEL PEREZ
Applicant returned to address corrections 8/11/2021 HELEN NGUYEN
Applicant returned to address corrections 11/5/2021 HELEN NGUYEN
Applicant returned to address corrections 11/16/2021 HELEN NGUYEN
Plan Check Approved 12/22/2021 HELEN NGUYEN
Issued 12/30/2021 APPLICANT
CofO in Progress 12/7/2022 CRAIG VAUGHAN
Permit Finaled 12/14/2022 DEROLD HAUFF
CofO Issued 12/14/2022 DEROLD HAUFF
Permit Finaled 12/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/24/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/24/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 6/24/2021 JEANIE LAM
Sewer availability Cleared 6/24/2021 JEANIE LAM
Grading Pre-Inspection Cleared 10/8/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Puliyadi,, Senthilnath Surendran; Lic. No.: C71630 22320 FOOTHILL BLVD STE 600      HAYWARD, CA 94541

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/9/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/10/2022 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/15/2022 Corrections Issued CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/22/2022 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/4/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 5/31/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/31/2022 Corrections Issued CRAIG VAUGHAN
Green Building Rough 5/31/2022 Approved CRAIG VAUGHAN
HVAC-Rough 5/31/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 5/31/2022 Approved CRAIG VAUGHAN
Wood Frame 5/31/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 6/16/2022 Approved CRAIG VAUGHAN
HVAC-Rough 6/16/2022 Partial Approval CRAIG VAUGHAN
Insulation 7/1/2022 Conditional Approval AMY COLIN
Drywall Nailing 7/21/2022 Approved KATHRYN BUTTERWORTH
Insulation 7/21/2022 Approved KATHRYN BUTTERWORTH
Final 11/8/2022 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 11/8/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 11/8/2022 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 11/8/2022 Approved KATHRYN BUTTERWORTH
Final 11/17/2022 Partial Approval KATHRYN BUTTERWORTH