20966 W COSTANSO ST 91364

Certificate Information: 20966 W COSTANSO ST 91364

Application / Permit
21014-10000-01750
Plan Check / Job No.
B21LA06563
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
266 SQ FT ADDITION AND CONVERSTION OF EXISTING 400 SQ FT GARAGE INTO ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c)(d) and (g)
Permit Issued
Issued on 1/19/2022
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 VARAND SARKISIAN
Corrections Issued 5/17/2021 VARAND SARKISIAN
Quality Review Completed 5/24/2021 HANS SANTIAGO
Building Plans Picked Up 5/25/2021 APPLICANT
Applicant returned to address corrections 9/30/2021 VARAND SARKISIAN
Plan Check Approved 11/15/2021 VARAND SARKISIAN
Issued 1/19/2022 APPLICANT
CofO in Progress 12/31/2022 PETER FOLLING
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/4/2021 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 6/4/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/4/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/4/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 8/20/2021 GILBERT URREA
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Sewer availability Cleared 11/12/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Restoration Masters Inc; Lic. No.: 934994-B 24313 MAIN ST #C      NEWHALL, CA 91321
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2022 Corrections Issued PETER FOLLING
PLUMBING-Rough 1/27/2022 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 No Access for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Approved PETER FOLLING
Footing/Foundation/Slab 4/21/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 6/7/2022 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 6/7/2022 Corrections Issued ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Not Ready for Inspection ROBERT GOLD
Green Building Rough 6/7/2022 Not Ready for Inspection ROBERT GOLD
MERV13>=Rough 6/7/2022 Corrections Issued ROBERT GOLD
PLUMBING-Rough 6/7/2022 Corrections Issued ROBERT GOLD
ELECTRICAL-Rough 6/14/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Approved PETER FOLLING
HVAC-Rough 6/14/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 6/30/2022 Approved PETER FOLLING
Green Building Rough 6/30/2022 Approved PETER FOLLING
Interior/Exterior Lathing 6/30/2022 Not Ready for Inspection PETER FOLLING
MERV13>=Rough 6/30/2022 Approved PETER FOLLING
PLUMBING-Rough 6/30/2022 Approved PETER FOLLING
Insulation 7/7/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/7/2022 Partial Approval MORRIS JACKSON
Drywall Nailing 7/15/2022 Approved PETER FOLLING
Interior/Exterior Lathing 7/15/2022 Approved PETER FOLLING
Final 11/28/2022 Corrections Issued VINCENT HANLEY
Green Building Final 11/28/2022 Approved VINCENT HANLEY
MERV13>=Final 11/28/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 11/28/2022 Approved VINCENT HANLEY
Final 12/29/2022 Partial Approval PETER FOLLING
Final 12/30/2022 OK to Issue CofO PETER FOLLING