20966 W COSTANSO ST 91364
Certificate Information: 20966 W COSTANSO ST 91364
- Application / Permit
- 21014-10000-01750
- Plan Check / Job No.
- B21LA06563
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 266 SQ FT ADDITION AND CONVERSTION OF EXISTING 400 SQ FT GARAGE INTO ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c)(d) and (g)
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | VARAND SARKISIAN |
| Corrections Issued | 5/17/2021 | VARAND SARKISIAN |
| Quality Review Completed | 5/24/2021 | HANS SANTIAGO |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| Applicant returned to address corrections | 9/30/2021 | VARAND SARKISIAN |
| Plan Check Approved | 11/15/2021 | VARAND SARKISIAN |
| Issued | 1/19/2022 | APPLICANT |
| CofO in Progress | 12/31/2022 | PETER FOLLING |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 6/4/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/4/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 8/20/2021 | GILBERT URREA |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Sewer availability | Cleared | 11/12/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Restoration Masters Inc; Lic. No.: 934994-B | 24313 MAIN ST #C NEWHALL, CA 91321 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/27/2022 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 1/27/2022 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | No Access for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 4/21/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/7/2022 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 6/7/2022 | Corrections Issued | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2022 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | ROBERT GOLD |
| MERV13>=Rough | 6/7/2022 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 6/7/2022 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 6/14/2022 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 6/14/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 6/30/2022 | Approved | PETER FOLLING |
| Green Building Rough | 6/30/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 6/30/2022 | Not Ready for Inspection | PETER FOLLING |
| MERV13>=Rough | 6/30/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 6/30/2022 | Approved | PETER FOLLING |
| Insulation | 7/7/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/7/2022 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 7/15/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 7/15/2022 | Approved | PETER FOLLING |
| Final | 11/28/2022 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 11/28/2022 | Approved | VINCENT HANLEY |
| MERV13>=Final | 11/28/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 11/28/2022 | Approved | VINCENT HANLEY |
| Final | 12/29/2022 | Partial Approval | PETER FOLLING |
| Final | 12/30/2022 | OK to Issue CofO | PETER FOLLING |