10522 W RAINIER ST 91352
Certificate Information: 10522 W RAINIER ST 91352
- Application / Permit
- 21014-10000-01742
- Plan Check / Job No.
- B21LA06520
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADDITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 9/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2021 | SINA KHOSRAVI |
| Corrections Issued | 4/14/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 11/1/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 2/9/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Applicant returned to address corrections | 7/19/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 9/20/2022 | STANLEY RAAP |
| Issued | 9/20/2022 | APPLICANT |
| CofO in Progress | 5/9/2023 | DAVID ANDERSON |
| Permit Finaled | 5/11/2023 | MICHAEL SMITH |
| CofO Issued | 5/11/2023 | MICHAEL SMITH |
| Permit Finaled | 5/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/27/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/29/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/15/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/3/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/3/2022 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 11/22/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 11/29/2022 | Partial Approval | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 12/30/2022 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 12/30/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/10/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 2/10/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 2/10/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 2/10/2023 | Approved | DAVID ANDERSON |
| Gas Test | 2/22/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/22/2023 | Corrections Issued | DAVID ANDERSON |
| Underground Mechanical | 2/22/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 2/27/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 2/27/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 2/27/2023 | Approved | DAVID ANDERSON |
| Insulation | 2/28/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 3/3/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 3/9/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/3/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 5/3/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 5/3/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 5/3/2023 | Approved | DAVID ANDERSON |
| HVAC-Final | 5/3/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 5/3/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 5/3/2023 | Approved | DAVID ANDERSON |
| Final | 5/8/2023 | OK to Issue CofO | DAVID ANDERSON |