5916 E PIEDMONT AVE 90042
Certificate Information: 5916 E PIEDMONT AVE 90042
- Application / Permit
- 21014-10000-01740
- Plan Check / Job No.
- B21LA06509
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- INTERIOR REMODEL TO (E) DUPLEX AND ADD WALKING DECK
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/6/2023
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | HERNAN ARREOLA |
| Corrections Issued | 5/5/2021 | HERNAN ARREOLA |
| Quality Review Completed | 5/5/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/11/2021 | APPLICANT |
| Applicant returned to address corrections | 6/22/2022 | HERNAN ARREOLA |
| Plan Check Approved | 8/24/2022 | HERNAN ARREOLA |
| Issued | 9/2/2022 | APPLICANT |
| Permit Finaled | 1/5/2023 | AMY COLIN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/25/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 5/31/2022 | ROBERT HUGHES |
| Metro Rail approval | Cleared | 6/13/2022 | HERNAN ARREOLA |
| HPOZ | Cleared | 8/10/2022 | KATIE DEBIASE |
| Specific Plan | Cleared | 8/25/2022 | PABLO ESTRADA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/9/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 11/9/2022 | Not Ready for Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Not Ready | AMY COLIN |
| Smoke Detectors | 11/9/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 12/29/2022 | Approved | AMY COLIN |
| Final | 12/29/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 12/29/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 12/29/2022 | Corrections Issued | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | AMY COLIN |
| Final | 1/5/2023 | Permit Finaled | AMY COLIN |