5469 S 8TH AVE 90043
Certificate Information: 5469 S 8TH AVE 90043
- Application / Permit
- 21014-10000-01733
- Plan Check / Job No.
- B21LA06480
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION AND REMODEL TO SFD
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 4/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | RICARDO RAMIREZ |
| Corrections Issued | 4/17/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 5/24/2021 | RICARDO RAMIREZ |
| Issued | 8/11/2021 | APPLICANT |
| Building Plans Picked Up | 8/18/2021 | APPLICANT |
| CofO in Progress | 3/7/2022 | HORACE FULTZ |
| Permit Finaled | 4/8/2022 | RONALD MYRICK |
| CofO Issued | 4/8/2022 | RONALD MYRICK |
| Permit Finaled | 4/8/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/18/2021 | CELINA MORENO |
| Sewer availability | Cleared | 5/18/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | CELINA MORENO |
| Hold | Cleared | 4/5/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12631 IMPERIAL HWY F-230 SANTA FE SPRINGS, CA 90670 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/30/2021 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 9/30/2021 | Approved | HORACE FULTZ |
| Insulation | 10/14/2021 | Partial Approval | ADAM ESCOTO |
| Underground Mechanical | 10/14/2021 | Partial Approval | ADAM ESCOTO |
| BUILDING-Rough-Frame | 11/15/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/15/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/15/2021 | Approved | ANTHONY EGSON |
| Pre-Inspection | 11/23/2021 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 11/23/2021 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 12/9/2021 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/27/2021 | Approved | HORACE FULTZ |
| Green Building Rough | 12/27/2021 | Approved | HORACE FULTZ |
| HVAC-Rough | 12/27/2021 | Approved | HORACE FULTZ |
| Insulation | 12/30/2021 | Corrections Issued | ADAM ESCOTO |
| Insulation | 1/4/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/4/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/6/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 1/13/2022 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 1/18/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 2/14/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Final | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 2/22/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/22/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 2/22/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 2/28/2022 | Approved | ANTHONY EGSON |
| Final | 2/28/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 2/28/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 2/28/2022 | Approved | ANTHONY EGSON |
| Pre-Inspection | 2/28/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 3/4/2022 | OK to Issue CofO | ANTHONY EGSON |