1909-1910 W ADAMS BLVD 90018

Certificate Information: 1909-1910 W ADAMS BLVD 90018

Application / Permit
21014-10000-01730
Plan Check / Job No.
B21LA06471
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
CONVERT PORTION OF WAREHOUSE TO CONDITIONED OFFICES, SHOWROOM, EXECUTIVE BATHROOM, AND (N) ADA UNISEX RESTROOMS. ADD 763 SF TO (E) MEZZANINE.
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
Issued on 4/7/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 ZAW HAN
Disabled Access Plans Picked Up 5/10/2021 APPLICANT
Corrections Issued 5/19/2021 ZAW HAN
Quality Review Completed 5/25/2021 KEN GILL
Building Plans Picked Up 6/2/2021 APPLICANT
Plan Check Approved 12/20/2021 ZAW HAN
Issued 4/7/2022 APPLICANT

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 6/16/2021 RAFAEL FONTES
ZA Case Cleared 6/16/2021 RAFAEL FONTES
ZI Cleared 6/16/2021 RAFAEL FONTES
Eng Process Fee Ord 176,300 Cleared 6/22/2021 WALLIE JONG
Highway dedication Cleared 6/22/2021 WALLIE JONG
Sewer availability Cleared 6/22/2021 WALLIE JONG
Low Impact Development Cleared 9/8/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/1/2021 WALLIE JONG
Green Code Cleared 11/29/2021 ZAW HAN
DAS Clearance Cleared 12/16/2021 ZAW HAN

Contact Information

Contractor Andersen Construction; Lic. No.: 460494-B 17455 LAKEWOOD BLVD      BELLFLOWER, CA 90706
Engineer Hanna,, Emil R; Lic. No.: C63602 18925 GRANADA CIRCLE      NORTHRIDGE, CA 91326

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 4/18/2022 Partial Inspection RUSSELL BONVOULOIR
METHANE-Rough 4/18/2022 Partial Inspection RUSSELL BONVOULOIR
Wood Frame 4/18/2022 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 4/19/2022 Conditional Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 4/25/2022 Approved TIMOTHY BUXTON
Green Building Rough 4/25/2022 Approved TIMOTHY BUXTON
Footing/Foundation/Slab 5/23/2022 Not Ready for Inspection RUSSELL BONVOULOIR
METHANE-Barrier 5/23/2022 Not Ready for Inspection RUSSELL BONVOULOIR
METHANE-Subgrade 5/23/2022 Not Ready for Inspection RUSSELL BONVOULOIR
Footing/Foundation/Slab 6/7/2022 Approved TIMOTHY BUXTON
METHANE-Barrier 6/7/2022 Approved TIMOTHY BUXTON
METHANE-Subgrade 6/7/2022 Approved TIMOTHY BUXTON
Deputy Steel/Welding 6/17/2022 Conditional Approval WINSTON DUNNING
Final 6/23/2022 Corrections Issued NICK DANERI
Green Building Final 6/23/2022 Not Ready for Inspection NICK DANERI
METHANE-Final 6/23/2022 Approved NICK DANERI
METHANE-Rough 6/23/2022 Approved NICK DANERI
Reinforced Masonry Frame 6/23/2022 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Not Ready NICK DANERI
Smoke Detectors 6/23/2022 Not Ready for Inspection NICK DANERI
Wood Frame 6/23/2022 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/7/2022 Corrections Issued RUSSELL BONVOULOIR
Final 2/7/2023 Partial Inspection MARTIN TAVITIAN
Green Building Final 2/7/2023 Approved MARTIN TAVITIAN
Reinforced Masonry Frame 2/7/2023 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 2/7/2023 Approved MARTIN TAVITIAN
Wood Frame 2/7/2023 Approved MARTIN TAVITIAN
Final 9/28/2023 Not Ready for Inspection MARTIN TAVITIAN
Final 6/28/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 7/11/2024 Corrections Issued DARRYL ARNOLD
Final 7/16/2024 Partial Approval ALFREDO LOPEZ