11043 W HATTERAS ST 91601

Certificate Information: 11043 W HATTERAS ST 91601

Application / Permit
21014-10000-01715
Plan Check / Job No.
B21LA06404
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of detached garage to DETACHED ADU with addition (1-STORY) PER ORDINANCE
Permit Issued
Issued on 12/19/2021
Issuing Office
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 CARLOS MONTES
Corrections Issued 5/20/2021 CARLOS MONTES
Quality Review Completed 5/21/2021 WING SUEN
Plan Check Approved 11/4/2021 CARLOS MONTES
Issued 12/19/2021 APPLICANT
CofO in Progress 8/22/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 9/5/2024 DANIEL ORRANTE
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/19/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/19/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/20/2021 CARLOS AGUILERA
Sewer availability Cleared 7/20/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Daye,, Jacob Charles; Lic. No.: C86191 21051 NEWLAND STREET   #178    HUNTINGTON BEACH, CA 92646

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/12/2022 Conditional Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 4/13/2022 Corrections Issued MATT KELLERMAN
Footing/Foundation/Slab 4/13/2022 Partial Approval MATT KELLERMAN
PLUMBING-Rough 4/19/2022 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 4/25/2022 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 5/19/2022 Corrections Issued CALEB MEISTER
Sewer 5/19/2022 Approved CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Partial Approval JORDAN KUTZLY
HVAC-Rough 1/27/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 2/6/2023 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 4/3/2023 Approved ROBERT GOLD
PLUMBING-Rough 5/4/2023 Corrections Issued THOMAS FINNILA
Underground Mechanical 5/4/2023 Partial Approval THOMAS FINNILA
PLUMBING-Rough 5/10/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 6/6/2023 Approved JOHN HAYES
Green Building Rough 6/6/2023 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 6/6/2023 Approved JOHN HAYES
Insulation 7/5/2023 Approved RYAN SALAZAR
Drywall Nailing 8/18/2023 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/18/2023 Approved KEVIN BERBERYAN
Underground Mechanical 11/29/2023 Corrections Issued JENNIFER RABUCHIN
Grounding or Bonding 12/29/2023 Approved CRAIG DAVIS
Underground Mechanical 12/29/2023 Approved CRAIG DAVIS
ELECTRICAL-Final 4/24/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 4/24/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 4/24/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 4/24/2024 Approved JENNIFER RABUCHIN
Final 7/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/16/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 8/21/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/21/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/21/2024 Approved ROBERTO PALACIOS-LOPEZ