300 S WESTGATE AVE 90049
Certificate Information: 300 S WESTGATE AVE 90049
- Application / Permit
- 21014-10000-01708
- Plan Check / Job No.
- B21LA06387
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 3 BDRM- 4 BATH TO THE EXISTING 3 BDRM - 3 1/2 BATH + 2 CAR GARAGE + 1398 SF BASEMENT
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 4/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 5/4/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/6/2021 | FARUK SEZER |
| Building Plans Picked Up | 5/10/2021 | APPLICANT |
| Applicant returned to address corrections | 6/16/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/17/2021 | SERGIO GUTIERREZ |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 4/28/2025 | MICHAEL PELHAM |
| Permit Finaled | 4/28/2025 | RICHARD STEINBACH |
| CofO Issued | 4/28/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/28/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | DINAH GARIN |
| Sewer availability | Cleared | 6/10/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 7/13/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 9/10/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/14/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 9/17/2021 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 9/17/2021 | SERGIO GUTIERREZ |
| Specific Plan | Cleared | 9/17/2021 | PEDRO AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Pezeshkian,, Vahik; Lic. No.: C35278 | 1545 N VERDUGO RD 217 GLENDALE, CA 91208 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| ANDREW NAVE, (310) 914-3908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 5/9/2022 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 6/8/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/8/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 6/13/2022 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/14/2022 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 6/15/2022 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2022 | Partial Approval | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 7/13/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 7/14/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 7/15/2022 | Conditional Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/15/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 8/16/2022 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Conditional Approval | CARLOS MATAMOROS |
| Pre-Inspection | 9/6/2022 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Shotcrete | 9/20/2022 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 10/24/2022 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/2/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/21/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2023 | Corrections Issued | CARLOS MATAMOROS |
| Drywall Nailing | 3/24/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/24/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Wood Construction | 3/28/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 3/31/2023 | Conditional Approval | MICHAEL PELHAM |
| Special/Order Compliance | 4/12/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2023 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 5/22/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 5/31/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 6/12/2023 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/30/2023 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 6/30/2023 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 6/30/2023 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/12/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 7/12/2023 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 7/12/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/14/2023 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 7/14/2023 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 7/14/2023 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 7/14/2023 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 7/14/2023 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 7/26/2023 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 7/26/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Interior/Exterior Lathing | 7/26/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| PLUMBING-Rough | 7/26/2023 | Partial Approval | MICHAEL PELHAM |
| HVAC-Rough | 7/31/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 7/31/2023 | Partial Approval | MICHAEL PELHAM |
| Interior/Exterior Lathing | 9/11/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/11/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/19/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Sewer | 10/19/2023 | Corrections Issued | MICHAEL PELHAM |
| Shower Pan | 10/19/2023 | Corrections Issued | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 10/19/2023 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/24/2023 | Corrections Issued | MICHAEL PELHAM |
| Green Building Rough | 10/24/2023 | Corrections Issued | MICHAEL PELHAM |
| Sewer | 10/24/2023 | Approved | MICHAEL PELHAM |
| Shower Pan | 10/24/2023 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 11/6/2023 | Partial Approval | MICHAEL PELHAM |
| Green Building Rough | 11/6/2023 | Approved | MICHAEL PELHAM |
| HVAC-Rough | 11/6/2023 | Approved | MICHAEL PELHAM |
| Insulation | 11/20/2023 | Corrections Issued | MICHAEL PELHAM |
| Drywall Nailing | 12/5/2023 | Partial Approval | MICHAEL PELHAM |
| Insulation | 12/22/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/22/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 12/26/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 12/26/2023 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 5/1/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| Gas Test | 5/1/2024 | Approved | MICHAEL PELHAM |
| Service/Power Release | 6/7/2024 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 9/30/2024 | Approved | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 9/30/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Shotcrete | 9/30/2024 | Conditional Approval | MICHAEL PELHAM |
| Final | 9/30/2024 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Final | 10/8/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 10/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Smoke Detectors | 10/8/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 10/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 11/13/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 11/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 11/26/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Final | 11/27/2024 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 11/27/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 2/11/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Final | 2/13/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 2/18/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 3/7/2025 | Partial Approval | SEAN HAUPT |
| Final | 3/15/2025 | Corrections Issued | MICHAEL PELHAM |
| Final | 4/28/2025 | OK to Issue CofO | MICHAEL PELHAM |