2810 S BENTLEY AVE 90064
Certificate Information: 2810 S BENTLEY AVE 90064
- Application / Permit
- 21014-10000-01706
- Plan Check / Job No.
- B21LA06383
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 6/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | DANIEL YIP |
| Corrections Issued | 4/27/2021 | DANIEL YIP |
| Quality Review Completed | 4/28/2021 | JASON HEALEY |
| Applicant returned to address corrections | 10/7/2021 | DANIEL YIP |
| Plan Check Approved | 10/8/2021 | DANIEL YIP |
| Issued | 10/19/2021 | APPLICANT |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| CofO in Progress | 6/28/2022 | JOHNNY MIRANDA |
| Permit Finaled | 6/29/2022 | DANIEL ORRANTE |
| CofO Issued | 6/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/13/2021 | KEVIN ARUCAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/14/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 9/30/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 10/7/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 10/7/2021 | DANIEL YIP |
Contact Information
| Architect | , ; Lic. No.: C37928 | 3131 FOOTHILL BLVD #L LA CRESCENTA, CA 91214 |
| Contractor | Orum Construction Group Inc; Lic. No.: 984353-B | 2001 SANTA ANA AVE STE 202 SOUTH EL MONTE, CA 91733 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/28/2021 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/29/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/10/2021 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 11/10/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/12/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Approved | JOHNNY MIRANDA |
| Wood Frame | 11/29/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/4/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 1/4/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/4/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/7/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 1/7/2022 | Approved | EVAN COOPER |
| Green Building Rough | 1/7/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 1/7/2022 | Approved | EVAN COOPER |
| MERV13>=Rough | 1/7/2022 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 1/7/2022 | Corrections Issued | EVAN COOPER |
| Wood Frame | 1/7/2022 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 1/18/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 1/18/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/18/2022 | Partial Approval | JOHNNY MIRANDA |
| MERV13>=Rough | 1/18/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 1/18/2022 | Approved | JOHNNY MIRANDA |
| Wood Frame | 1/18/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 1/24/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 2/1/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 3/24/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Final | 3/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 3/25/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 4/1/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 4/1/2022 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 4/1/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 5/12/2022 | Approved | JOHNNY MIRANDA |
| Final | 5/12/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/12/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 5/12/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 5/12/2022 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Final | 5/12/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 5/12/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 6/21/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 6/21/2022 | Approved | JOHNNY MIRANDA |
| Final | 6/27/2022 | OK to Issue CofO | JOHNNY MIRANDA |