2047 W 95TH ST 90047
Certificate Information: 2047 W 95TH ST 90047
- Application / Permit
- 21014-10000-01652
- Plan Check / Job No.
- B21LA06194
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SFD INTERIOR REMODEL + ADDITION -NEW PLUMBING, ELECTRICAL & COSMETIC 1 OF 2
- Permit Issued
- Issued on 6/17/2021
- Issuing Office
- Current Status
- CofO Issued on 2/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 4/22/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/27/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 6/3/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 6/8/2021 | ARSALAN SHABESTARI |
| Issued | 6/17/2021 | APPLICANT |
| Building Plans Picked Up | 6/21/2021 | APPLICANT |
| CofO in Progress | 9/20/2022 | ENRIQUE MIRELES |
| Permit Finaled | 2/22/2023 | DEROLD HAUFF |
| CofO Issued | 2/22/2023 | DEROLD HAUFF |
| Permit Finaled | 2/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 5/13/2021 | WALLIE JONG |
| Sewer availability | Cleared | 5/13/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/23/2021 | Partial Inspection | DAVID FEILER |
| Deputy Drilled-In Anchors | 7/12/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 7/13/2021 | No Access for Inspection | FREDDIE RIVERA |
| METHANE-Barrier | 7/13/2021 | No Access for Inspection | FREDDIE RIVERA |
| METHANE-Subgrade | 7/13/2021 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/16/2021 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 7/16/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/4/2021 | Order to Comply Issued | FREDDIE RIVERA |
| Green Building Rough | 8/4/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Rough | 8/4/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 8/9/2021 | Partial Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 8/19/2021 | Conditional Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Partial Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 8/25/2021 | Conditional Approval | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 9/22/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/1/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 10/1/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/14/2021 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 10/28/2021 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 10/28/2021 | Approved | FREDDIE RIVERA |
| Insulation | 11/9/2021 | No Access for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 11/12/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/12/2021 | Order to Comply Issued | FREDDIE RIVERA |
| Drywall Nailing | 12/8/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 12/8/2021 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/13/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 12/13/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/15/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 12/15/2021 | Approved | FREDDIE RIVERA |
| Final | 6/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Green Building Final | 6/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 6/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Smoke Detectors | 6/21/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 7/26/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 7/29/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 7/29/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 7/29/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 7/29/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 7/29/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 8/5/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 8/5/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/5/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 8/5/2022 | Approved | ENRIQUE MIRELES |
| Final | 8/15/2022 | Corrections Issued | ENRIQUE MIRELES |
| Final | 9/19/2022 | OK to Issue CofO | ENRIQUE MIRELES |