1397 W 2ND ST 90732
Certificate Information: 1397 W 2ND ST 90732
- Application / Permit
- 21014-10000-01619
- Plan Check / Job No.
- B21LA06052
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND ADDITION TO (E) 1-STORY SFD
- Permit Issued
- Issued on 2/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | KHEDER ALRAZAA |
| Corrections Issued | 5/6/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 5/11/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/14/2021 | APPLICANT |
| Plan Check Approved | 1/10/2022 | KHEDER ALRAZAA |
| Issued | 2/2/2022 | APPLICANT |
| CofO in Progress | 12/20/2022 | ANSON MAGLASANG |
| CofO Issued | 12/21/2022 | DEROLD HAUFF |
| Permit Finaled | 12/21/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/14/2021 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 7/8/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | CHINH DINH |
| Grading Pre-Inspection | Cleared | 8/11/2021 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 1/4/2022 | MARCO SANCHEZ |
Contact Information
| Contractor | Martin B Construction; Lic. No.: 530578-B | 24212 ALLIENE LOMITA, CA 90717 |
| Engineer | Chaiprasert,, Victor V; Lic. No.: C36235 | 17703 CRENSHAW BLVD TORRANCE, CA 90504 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/11/2022 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/16/2022 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 5/16/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 5/16/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 5/16/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 5/16/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Deputy Wood Construction | 5/18/2022 | Conditional Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 5/20/2022 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Rough | 5/20/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 5/20/2022 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 5/20/2022 | Approved | ANSON MAGLASANG |
| PLUMBING-Rough | 5/20/2022 | Approved | ANSON MAGLASANG |
| Insulation | 6/3/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/3/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/14/2022 | Approved | EUGENE CASSIDY |
| Gas Test | 8/2/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Shower Pan | 8/2/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 8/9/2022 | Partial Approval | ANSON MAGLASANG |
| HVAC-Final | 11/1/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Final | 11/1/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Service/Power Release | 11/1/2022 | Approved | ANSON MAGLASANG |
| Gas Test | 11/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 12/20/2022 | OK to Issue CofO | ANSON MAGLASANG |
| Footing/Foundation/Slab | 12/20/2022 | Approved | ANSON MAGLASANG |
| Green Building Final | 12/20/2022 | Approved | ANSON MAGLASANG |
| HVAC-Final | 12/20/2022 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/20/2022 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 12/20/2022 | Approved | ANSON MAGLASANG |