551 W 89TH ST 90044
Certificate Information: 551 W 89TH ST 90044
- Application / Permit
- 21014-10000-01616
- Plan Check / Job No.
- B21LA06039
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED 2-CAR GARAGE WITH ADDITION TO ACCESSORY DWELLING UNIT PER ORDINANCE AND LAMC 12.22 A33(c)&(d) . All work per WFPP
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Metro
- Current Status
- Issued on 9/23/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2021 | ZAW HAN |
| Corrections Issued | 4/15/2021 | ZAW HAN |
| Building Plans Picked Up | 4/19/2021 | APPLICANT |
| Applicant returned to address corrections | 5/27/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 3/29/2022 | JESSE JIMENEZ |
| Plan Check Approved | 9/20/2022 | GEORGE ALVAREZ |
| Issued | 9/23/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2022 | CINDY QI |
| Sewer availability | Cleared | 4/28/2022 | CINDY QI |
| Community Plan Implem. Overlay | Cleared | 5/11/2022 | RAFAEL FONTES |
| ZI | Cleared | 5/11/2022 | RAFAEL FONTES |
| Low Impact Development | Cleared | 9/16/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/19/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 6/6/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/26/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/13/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/13/2023 | Partial Approval | MICHAEL LEWIS |
| Sewer | 10/13/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 11/17/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/17/2023 | Partial Approval | MICHAEL LEWIS |
| Underground Mechanical | 12/14/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/26/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| HVAC-Rough | 11/26/2024 | Partial Approval | MICHAEL LEWIS |
| HVAC-Rough | 12/2/2024 | Approved | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 12/9/2024 | Conditional Approval | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 12/10/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 12/10/2024 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 1/7/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 1/7/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 1/15/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 1/15/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 1/31/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 5/19/2025 | Approved | MICHAEL LEWIS |
| Shower Pan | 5/19/2025 | Approved | MICHAEL LEWIS |
| Gas Test | 5/20/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Gas Test | 3/6/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Final | 3/6/2026 | Partial Approval | JOHN QUINTANILLA |
| ELECTRICAL-Final | 4/10/2026 | Corrections Issued | JOHN QUINTANILLA |
| Gas Test | 4/10/2026 | Approved | JOHN QUINTANILLA |