2022 S WEST VIEW ST 90016
Certificate Information: 2022 S WEST VIEW ST 90016
- Application / Permit
- 21014-10000-01606
- Plan Check / Job No.
- B21LA06008
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: PROPOSED ADU 2ND STORY ADDITION TO EXISTING GARAGE LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 2/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 5/23/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 6/3/2021 | WING SUEN |
| Applicant returned to address corrections | 1/4/2022 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 1/28/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/7/2022 | CRYSTEL MAALOUF |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 1/31/2024 | JUSTIN HAWLEY |
| No Progress | 2/5/2024 | DEROLD HAUFF |
| CofO in Progress | 2/5/2024 | DEROLD HAUFF |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
| CofO Issued | 2/5/2024 | DEROLD HAUFF |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2021 | CELINA MORENO |
| Highway dedication | Cleared | 7/16/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 7/16/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/25/2022 | LAURINDA MEADE |
| Sewer availability | Cleared | 2/25/2022 | CELINA MORENO |
| Abandoned oil well | Cleared | 3/3/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Kor Design Build; Lic. No.: 1026877-B | , |
| Engineer | Naeem,, Samer Atef; Lic. No.: C88038 | 3928 N HARTLEY AVE COVINA, CA 91722 |
| Engineer | Naeem,, Samer Atef; Lic. No.: NA88038 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/8/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 6/14/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/21/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/23/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Wood Construction | 2/9/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Wood Construction | 2/21/2023 | Conditional Approval | CALEB MEISTER |
| Deputy Wood Construction | 3/2/2023 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 4/13/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 6/21/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 6/21/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 6/21/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 7/3/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 7/3/2023 | Approved | CALEB MEISTER |
| HVAC-Final | 7/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 7/3/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 7/3/2023 | Partial Approval | CALEB MEISTER |
| Insulation | 7/13/2023 | Corrections Issued | CALEB MEISTER |
| Drywall Nailing | 7/26/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Final | 10/27/2023 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Final | 11/2/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/2/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/2/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Final | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Final | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 11/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 12/22/2023 | Approved | JUSTIN HAWLEY |
| Final | 12/22/2023 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 12/22/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 12/22/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 1/9/2024 | Approved | SCOTT FINNILA |
| Final | 1/9/2024 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 1/9/2024 | Approved | SCOTT FINNILA |
| Green Building Final | 1/9/2024 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 1/9/2024 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 1/9/2024 | Approved | SCOTT FINNILA |
| Final | 1/30/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| HVAC-Final | 1/30/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 1/30/2024 | Approved | JUSTIN HAWLEY |