4250 N NAVAJO ST 91602
Certificate Information: 4250 N NAVAJO ST 91602
- Application / Permit
- 21014-10000-01580
- Plan Check / Job No.
- B21LA05951
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ALTERATION OF EXISTING GROUND LEVEL KITCHEN 550 SF. ENCLOSE EXISTING COVERED BALCONY AT SECOND FLOOR 57 SF. REPLACE EXISTING ROOF FROM CONCRETE TILE TO ZINC METAL ROOF. REPLACE ALL EXISTING WINDOWS AND EXTERIOR DOORS
- Permit Issued
- Issued on 8/23/2021
- Issuing Office
- Current Status
- Issued on 8/23/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 4/9/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/26/2021 | JOE VO |
| Issued | 8/23/2021 | APPLICANT |
| Building Plans Picked Up | 9/15/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Providence Construction Group; Lic. No.: 950289-B | 16701 ALEXANDER AVENUE CERRITOS, CA 90703 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/17/2021 | Partial Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/30/2021 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 10/4/2021 | Approved | MICHAEL PELHAM |
| Special/Order Compliance | 10/4/2021 | Approved | MATTHEW NELSON |
| Deputy Steel/Welding | 10/14/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Inspection | THOMAS FINNILA |
| Sewer | 11/15/2021 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Partial Inspection | CALEB MEISTER |
| Deputy Steel/Welding | 10/5/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/1/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/9/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/9/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/9/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/9/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/23/2024 | Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 10/23/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/26/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 11/26/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Steel/Welding | 12/10/2024 | Conditional Approval | ROBERT GOLD |
| Drywall Nailing | 12/17/2024 | Approved | MICHAEL CORTEZ |
| Deputy Steel/Welding | 12/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Steel/Welding | 12/20/2024 | Conditional Approval | JUAN VALENZUELA |
| Shower Pan | 12/30/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 1/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Gas Test | 7/10/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/14/2025 | Approved | JAVIER RAMOS JR |
| Final | 11/14/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/14/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 11/14/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 11/14/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/14/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/14/2025 | Approved | JAVIER RAMOS JR |