2640 S MIDVALE AVE 90064
Certificate Information: 2640 S MIDVALE AVE 90064
- Application / Permit
- 21014-10000-01578
- Plan Check / Job No.
- B21LA05941
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW EXTERIOR TRI-FOLD DOOR @ MASTER BEDROOM. ADD UNCOVERED LATTICE ROOF PERGOLA (12' X 9') TO THE REAR.
- Permit Issued
- Issued on 7/16/2021
- Issuing Office
- Current Status
- CofO Issued on 6/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 4/11/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 5/18/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 5/26/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 6/1/2021 | APPLICANT |
| Plan Check Approved | 6/17/2021 | SAMUEL GONZALEZ |
| Issued | 7/16/2021 | APPLICANT |
| Permit Finaled | 6/25/2025 | RICHARD STEINBACH |
| CofO Issued | 6/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/16/2021 | JESSE JIMENEZ |
Contact Information
| Contractor | Delta Remodeling Inc; Lic. No.: 913496-B | 8309 TUJUNGA AVENUE #105 SUN VALLEY, CA 91352 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/10/2021 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/12/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Piling/Pier/Caisson | 8/12/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Wood Frame | 8/12/2021 | Partial Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/17/2021 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/17/2021 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 8/17/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/23/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/6/2021 | Not Ready for Inspection | EVAN COOPER |
| Wood Frame | 10/6/2021 | Conditional Approval | EVAN COOPER |
| Interior/Exterior Lathing | 10/8/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/21/2021 | Approved | RYAN SALAZAR |
| Final | 6/10/2022 | Conditional Approval | JOHNNY MIRANDA |
| Smoke Detectors | 6/10/2022 | Approved | JOHNNY MIRANDA |
| Wood Frame | 6/10/2022 | Approved | JOHNNY MIRANDA |