9312 W AIRDROME ST 90035
Certificate Information: 9312 W AIRDROME ST 90035
- Application / Permit
- 21014-10000-01577
- Plan Check / Job No.
- B21LA05939
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED 2-STORY DETACHED ACCESSORY DWELLING UNIT PER ORDININACE.
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | MICHAEL LOPEZ |
| Corrections Issued | 5/20/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 5/27/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/24/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/7/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/11/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/4/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 5/4/2022 | TEODORO DIAZ RODRIGUEZ |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 8/14/2023 | DAVID FEILER |
| Permit Finaled | 8/22/2023 | DANIEL ORRANTE |
| CofO Issued | 8/22/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/22/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction within easement | Cleared | 8/25/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/8/2021 | CHRIS VONG |
| Address approval | Cleared | 10/14/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 10/18/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/18/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 10/22/2021 | KURT CORRAL |
| GPI Written Notices | Cleared | 11/23/2021 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 11/23/2021 | MATTHEW JENKINS |
Contact Information
| Architect | Lee,, Kenneth David; Lic. No.: NA10141 | , |
| Contractor | Drexel Construction Management Llc; Lic. No.: 1014160-B | 5168 W PICO BLVD LOS ANGELES, CA 90019 |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/20/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/1/2022 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 7/28/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 8/17/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/17/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 1/17/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 1/17/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/2/2023 | Corrections Issued | JEREMY TODD |
| ELECTRICAL-Rough | 2/2/2023 | Approved | JEREMY TODD |
| Green Building Rough | 2/2/2023 | Approved | JEREMY TODD |
| HVAC-Rough | 2/2/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 2/2/2023 | Approved | JEREMY TODD |
| Verify Sprinkler Sign Off | 2/2/2023 | Conditional Approval | JEREMY TODD |
| HVAC-Rough | 2/3/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/17/2023 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 2/17/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/9/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 3/14/2023 | Conditional Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/14/2023 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 3/14/2023 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 3/14/2023 | Partial Inspection | JESUS PINEDA |
| Insulation | 4/20/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/20/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 4/27/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 7/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 7/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Final | 7/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| PLUMBING-Final | 7/7/2023 | Corrections Issued | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Not Ready | CLAYTON GRAHAM |
| Service/Power Release | 7/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Smoke Detectors | 7/7/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 7/12/2023 | Corrections Issued | ARAM AVEDISIAN |
| Final | 7/12/2023 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 7/12/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 7/12/2023 | Approved | ARAM AVEDISIAN |
| Final | 7/21/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 7/21/2023 | Approved | ARAM AVEDISIAN |
| Green Building Final | 7/21/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 7/21/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 8/11/2023 | Approved | CLAYTON GRAHAM |
| Final | 8/11/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| HVAC-Final | 8/11/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 8/11/2023 | Approved | CLAYTON GRAHAM |