8551 W KYLE ST 91040

Certificate Information: 8551 W KYLE ST 91040

Application / Permit
21014-10000-01549
Plan Check / Job No.
B21LA05819
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-Plan: Proposed Garage conversion to ADU per ordinance with an addition to the rear.
Permit Issued
Issued on 9/29/2021
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 MICHAEL LOPEZ
Corrections Issued 5/7/2021 MICHAEL LOPEZ
Quality Review Completed 5/12/2021 HERNAN ARREOLA
Applicant returned to address corrections 7/7/2021 MICHAEL LOPEZ
Plan Check Approved 9/21/2021 MICHAEL LOPEZ
Issued 9/29/2021 APPLICANT
CofO in Progress 8/7/2023 WILLIAM WREN
CofO Issued 9/12/2023 RUBEN SALAS
Permit Finaled 9/12/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/2/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/2/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/2/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/2/2021 DAGOVERTO GUERRERO
ZA Case Cleared 6/2/2021 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 6/7/2021 BRIAN MILLER
GPI Written Notices Cleared 7/4/2021 MICHAEL LOPEZ
Low Impact Development Cleared 9/3/2021 SUNG JOON WON

Contact Information

Architect Karabachian,, Sevak A; Lic. No.: NA38632       ,
Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: NA82796       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/11/2023 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 5/16/2023 Approved WILLIAM WREN
PLUMBING-Rough 5/16/2023 Partial Approval WILLIAM WREN
Gas Test 5/22/2023 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 5/22/2023 Not Ready for Inspection MATTHEW NELSON
Sewer 5/22/2023 Approved MATTHEW NELSON
Underground Mechanical 5/22/2023 Corrections Issued MATTHEW NELSON
Gas Test 5/30/2023 Partial Approval WILLIAM WREN
PLUMBING-Rough 5/30/2023 Not Ready for Inspection WILLIAM WREN
Underground Mechanical 5/30/2023 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 6/15/2023 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Approved WILLIAM WREN
PLUMBING-Rough 6/15/2023 Approved WILLIAM WREN
Shower Pan 6/15/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 6/21/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 6/21/2023 Approved WILLIAM WREN
Green Building Rough 6/21/2023 Approved WILLIAM WREN
HVAC-Rough 6/21/2023 Not Ready for Inspection WILLIAM WREN
Wood Frame 6/21/2023 Not Ready for Inspection WILLIAM WREN
Deputy Wood Construction 6/26/2023 Conditional Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Approved WILLIAM WREN
Insulation 6/27/2023 Approved WILLIAM WREN
Drywall Nailing 6/30/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 7/7/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 7/28/2023 Not Ready for Inspection WILLIAM WREN
Final 7/28/2023 Not Ready for Inspection WILLIAM WREN
Footing/Foundation/Slab 7/28/2023 Not Ready for Inspection WILLIAM WREN
Green Building Final 7/28/2023 Not Ready for Inspection WILLIAM WREN
HVAC-Final 7/28/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Final 7/28/2023 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 7/28/2023 SGSOV Not Ready WILLIAM WREN
Smoke Detectors 7/28/2023 Not Ready for Inspection WILLIAM WREN
Final 8/4/2023 OK to Issue CofO WILLIAM WREN
Footing/Foundation/Slab 8/4/2023 Approved WILLIAM WREN
Green Building Final 8/4/2023 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 8/4/2023 SGSOV Approved WILLIAM WREN
Service/Power Release 8/4/2023 Approved WILLIAM WREN
Smoke Detectors 8/4/2023 Approved WILLIAM WREN