1426 1/2 S SHERBOURNE DR 90035
Certificate Information: 1426 1/2 S SHERBOURNE DR 90035
- Application / Permit
- 21014-10000-01538
- Plan Check / Job No.
- B21LA05764
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING (E) 2-CAR GARAGE TO ADU PER LAMC 12.22 A.33 (c)-(d), ADD SECOND STORY ADDITION.
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Current Status
- CofO Issued on 5/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/22/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/1/2021 | JASON HEALEY |
| Building Plans Picked Up | 7/6/2021 | APPLICANT |
| Plan Check Approved | 4/17/2024 | MAHNAZ NOURHASHEMI |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 5/14/2025 | EVAN COOPER |
| CofO Issued | 5/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 3/29/2022 | CINDY QI |
| Sewer availability | Cleared | 3/29/2022 | CINDY QI |
| "Q" conditions | Cleared | 5/9/2022 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 5/27/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 2/5/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/5/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 2919 BURBANK BLVD STE D BURBANK, CA 91505 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2024 | Approved | MEL KHACHATOURIAN |
| Pre-Inspection | 8/29/2024 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 10/8/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 10/8/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 10/8/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 12/24/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 12/24/2024 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 12/24/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 12/24/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 12/24/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/24/2024 | Approved | MEL KHACHATOURIAN |
| Sewer | 12/24/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/16/2025 | Partial Approval | MEL KHACHATOURIAN |
| Shower Pan | 1/16/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Insulation | 1/30/2025 | Approved | SEAN HAUPT |
| Shower Pan | 1/30/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/5/2025 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 2/5/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/5/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 2/5/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/24/2025 | Approved | MEL KHACHATOURIAN |
| Final | 4/9/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 4/9/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/9/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/1/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Final | 5/1/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 5/1/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 5/1/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 5/14/2025 | Approved | EVAN COOPER |
| Final | 5/14/2025 | OK to Issue CofO | EVAN COOPER |
| PLUMBING-Final | 5/14/2025 | Approved | EVAN COOPER |