1711 W 242ND PL 90717

Certificate Information: 1711 W 242ND PL 90717

Application / Permit
21014-10000-01528
Plan Check / Job No.
B21LA05701
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL.
Permit Issued
Issued on 7/9/2021
Issuing Office
Current Status
CofO Issued on 6/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/30/2021 GEORGE ALVAREZ
Corrections Issued 4/13/2021 GEORGE ALVAREZ
Plan Check Approved 5/21/2021 SHANGQIN XIE
Plan Check Approved 7/9/2021 STELLA SARGSYAN
Issued 7/9/2021 APPLICANT
Building Plans Picked Up 7/14/2021 APPLICANT
CofO in Progress 5/19/2022 EUGENE CASSIDY
CofO Issued 6/3/2022 DEROLD HAUFF
Permit Finaled 6/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/27/2021 CHINH DINH
Sewer availability Cleared 4/27/2021 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 4/29/2021 CHINH DINH

Contact Information

Contractor Pure Energy Construction; Lic. No.: 1066309-B 21044 SHERMAN WAY #105      CANOGA PARK, CA 91303
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/14/2021 Approved JOHN KLARIN
METHANE-Barrier 7/14/2021 Approved JOHN KLARIN
METHANE-Subgrade 7/14/2021 Approved JOHN KLARIN
Deputy Reinf. Concrete 7/20/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval JOHN KLARIN
Insulation 8/10/2021 Partial Approval CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/8/2021 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 11/8/2021 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 11/8/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/18/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 11/18/2021 Approved JOHN KLARIN
Green Building Rough 11/18/2021 Approved JOHN KLARIN
METHANE-Rough 11/18/2021 Approved JOHN KLARIN
PLUMBING-Rough 11/18/2021 Approved JOHN KLARIN
Shower Pan 12/6/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 12/16/2021 Corrections Issued EUGENE CASSIDY
Insulation 12/27/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 12/27/2021 Approved JOHN KLARIN
Drywall Nailing 1/19/2022 Conditional Approval EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Not Ready EUGENE CASSIDY
Final 4/22/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 4/22/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 4/22/2022 Not Ready for Inspection EUGENE CASSIDY
Final 5/3/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 5/3/2022 Approved EUGENE CASSIDY
Smoke Detectors 5/3/2022 Approved EUGENE CASSIDY
Final 5/13/2022 OK to Issue CofO EUGENE CASSIDY