1711 W 242ND PL 90717
Certificate Information: 1711 W 242ND PL 90717
- Application / Permit
- 21014-10000-01528
- Plan Check / Job No.
- B21LA05701
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL.
- Permit Issued
- Issued on 7/9/2021
- Issuing Office
- Current Status
- CofO Issued on 6/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2021 | GEORGE ALVAREZ |
| Corrections Issued | 4/13/2021 | GEORGE ALVAREZ |
| Plan Check Approved | 5/21/2021 | SHANGQIN XIE |
| Plan Check Approved | 7/9/2021 | STELLA SARGSYAN |
| Issued | 7/9/2021 | APPLICANT |
| Building Plans Picked Up | 7/14/2021 | APPLICANT |
| CofO in Progress | 5/19/2022 | EUGENE CASSIDY |
| CofO Issued | 6/3/2022 | DEROLD HAUFF |
| Permit Finaled | 6/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/27/2021 | CHINH DINH |
| Sewer availability | Cleared | 4/27/2021 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2021 | CHINH DINH |
Contact Information
| Contractor | Pure Energy Construction; Lic. No.: 1066309-B | 21044 SHERMAN WAY #105 CANOGA PARK, CA 91303 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 7/14/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 7/14/2021 | Approved | JOHN KLARIN |
| Deputy Reinf. Concrete | 7/20/2021 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | JOHN KLARIN |
| Insulation | 8/10/2021 | Partial Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/8/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 11/8/2021 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 11/8/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 11/18/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 11/18/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 11/18/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 11/18/2021 | Approved | JOHN KLARIN |
| Shower Pan | 12/6/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 12/16/2021 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 12/27/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 12/27/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 1/19/2022 | Conditional Approval | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 4/22/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/22/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/22/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/3/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/3/2022 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 5/3/2022 | Approved | EUGENE CASSIDY |
| Final | 5/13/2022 | OK to Issue CofO | EUGENE CASSIDY |