826 E WARREN AVE 90291

Certificate Information: 826 E WARREN AVE 90291

Application / Permit
21014-10000-01515
Plan Check / Job No.
B21LA05674
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL EXISTING SINGLE FAMILY DWELLING. REFRAME PORTION OF ROOF AT FRONT. ENCLOSE PORTION OF FRONT PORCH .
Permit Issued
Issued on 11/1/2021
Issuing Office
Current Status
Permit Finaled on 9/12/2023

Permit Application Status History

Submitted 4/2/2021 APPLICANT
Assigned to Plan Check Engineer 4/10/2021 LAWRENCE QUIRANTE
Corrections Issued 4/10/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/27/2021 CRISTINA SALAZAR
Applicant returned to address corrections 7/10/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/13/2021 GEORGE ALVAREZ
Applicant returned to address corrections 9/8/2021 LAWRENCE QUIRANTE
Plan Check Approved 9/15/2021 LAWRENCE QUIRANTE
Issued 11/1/2021 APPLICANT
Building Plans Picked Up 11/2/2021 APPLICANT
Permit Finaled 9/8/2023 HERBERT GIRON
CofO in Progress 9/8/2023 HERBERT GIRON
CofO in Progress 9/12/2023 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/9/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/13/2021 SAUL GARCIA

Contact Information

Contractor Axmis Construction; Lic. No.: 1057810-B 5770 W CENTINELA AVE AP310      LOS ANGELES, CA 90045
Engineer Ibarra,, Marco Antonio; Lic. No.: C74010 16 N MARENGON AVE STE 604      PASADENA, CA 91101

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2021 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/12/2022 No Access for Inspection DAVID FEILER
Footing/Foundation/Slab 1/14/2022 Not Ready for Inspection DAVID FEILER
Deputy Reinf. Concrete 5/13/2022 No Access for Inspection DAVID FEILER
Deputy Wood Construction 5/13/2022 No Access for Inspection DAVID FEILER
BUILDING-Rough-Frame 8/29/2023 Approved HERBERT GIRON
Final 8/29/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 8/29/2023 Approved HERBERT GIRON
Green Building Final 8/29/2023 Approved HERBERT GIRON
Green Building Rough 8/29/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 8/29/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/8/2023 Approved HERBERT GIRON
Final 9/8/2023 Permit Finaled HERBERT GIRON
HVAC-Final 9/8/2023 Approved HERBERT GIRON
PLUMBING-Final 9/8/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 9/8/2023 Approved HERBERT GIRON