5402 N EBEY AVE 90042
Certificate Information: 5402 N EBEY AVE 90042
- Application / Permit
- 21014-10000-01509
- Plan Check / Job No.
- B21LA05670
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION AND INTERIOR AND EXTERIOR STRUCTURAL REMODEL PER PLAN.
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 5/6/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 5/12/2021 | JASON HEALEY |
| Building Plans Picked Up | 5/17/2021 | APPLICANT |
| Plan Check Approved | 9/20/2021 | MAHNAZ NOURHASHEMI |
| Issued | 2/21/2023 | APPLICANT |
| CofO in Progress | 12/26/2023 | AMY COLIN |
| No Progress | 1/5/2024 | AMY COLIN |
| CofO in Progress | 3/28/2024 | LILIANA PORTILLO |
| Permit Finaled | 4/1/2024 | DEROLD HAUFF |
| Permit Finaled | 4/1/2024 | DEROLD HAUFF |
| CofO Issued | 4/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/7/2021 | MAHNAZ NOURHASHEMI |
| Roof/Waste drainage to street | Cleared | 5/27/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2021 | STEVE MELGAR |
| "D" conditions | Cleared | 8/23/2021 | JASON CHAN |
| "Q" conditions | Cleared | 8/26/2021 | JASON CHAN |
Contact Information
| Contractor | A Grade Construction; Lic. No.: 925835-B | 1443 EAST WASHINGTON BLVD #107 PASADENA, CA 91104 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2023 | Partial Inspection | AMY COLIN |
| Deputy Drilled-In Anchors | 4/19/2023 | Conditional Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 4/19/2023 | Corrections Issued | AMY COLIN |
| Deputy Reinf. Concrete | 4/20/2023 | Conditional Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | AMY COLIN |
| Deputy Wood Construction | 7/6/2023 | Conditional Approval | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | AMY COLIN |
| Deputy Wood Construction | 8/18/2023 | Conditional Approval | AMY COLIN |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 9/1/2023 | Corrections Issued | AMY COLIN |
| Green Building Rough | 9/1/2023 | Not Ready for Inspection | AMY COLIN |
| HVAC-Rough | 9/1/2023 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 9/1/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 9/1/2023 | Approved | AMY COLIN |
| Shower Pan | 9/1/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 9/12/2023 | Approved | AMY COLIN |
| Insulation | 9/12/2023 | Approved | AMY COLIN |
| Drywall Nailing | 10/4/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 10/4/2023 | Approved | AMY COLIN |
| Green Building Rough | 10/4/2023 | Approved | AMY COLIN |
| HVAC-Rough | 10/4/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 10/4/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 10/27/2023 | Approved | AMY COLIN |
| Final | 12/20/2023 | OK to Issue CofO | AMY COLIN |
| Footing/Foundation/Slab | 12/20/2023 | Approved | AMY COLIN |
| Green Building Final | 12/20/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 12/20/2023 | Approved | AMY COLIN |
| Special/Order Compliance | 1/5/2024 | Corrections Issued | AMY COLIN |
| Final | 3/27/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Special/Order Compliance | 3/27/2024 | Approved | LILIANA PORTILLO |