5402 N EBEY AVE 90042

Certificate Information: 5402 N EBEY AVE 90042

Application / Permit
21014-10000-01509
Plan Check / Job No.
B21LA05670
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION AND INTERIOR AND EXTERIOR STRUCTURAL REMODEL PER PLAN.
Permit Issued
Issued on 2/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 MAHNAZ NOURHASHEMI
Corrections Issued 5/6/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 5/12/2021 JASON HEALEY
Building Plans Picked Up 5/17/2021 APPLICANT
Plan Check Approved 9/20/2021 MAHNAZ NOURHASHEMI
Issued 2/21/2023 APPLICANT
CofO in Progress 12/26/2023 AMY COLIN
No Progress 1/5/2024 AMY COLIN
CofO in Progress 3/28/2024 LILIANA PORTILLO
Permit Finaled 4/1/2024 DEROLD HAUFF
Permit Finaled 4/1/2024 DEROLD HAUFF
CofO Issued 4/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/7/2021 MAHNAZ NOURHASHEMI
Roof/Waste drainage to street Cleared 5/27/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/2/2021 STEVE MELGAR
"D" conditions Cleared 8/23/2021 JASON CHAN
"Q" conditions Cleared 8/26/2021 JASON CHAN

Contact Information

Contractor A Grade Construction; Lic. No.: 925835-B 1443 EAST WASHINGTON BLVD #107      PASADENA, CA 91104
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/11/2023 Partial Inspection AMY COLIN
Deputy Drilled-In Anchors 4/19/2023 Conditional Approval RUBEN SALAS
Excavation/Setback/Form/Re-Bar 4/19/2023 Corrections Issued AMY COLIN
Deputy Reinf. Concrete 4/20/2023 Conditional Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 5/15/2023 Partial Approval AMY COLIN
Deputy Wood Construction 7/6/2023 Conditional Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval AMY COLIN
Deputy Wood Construction 8/18/2023 Conditional Approval AMY COLIN
BUILDING-Rough-Frame 9/1/2023 Approved AMY COLIN
ELECTRICAL-Rough 9/1/2023 Corrections Issued AMY COLIN
Green Building Rough 9/1/2023 Not Ready for Inspection AMY COLIN
HVAC-Rough 9/1/2023 Corrections Issued AMY COLIN
Interior/Exterior Lathing 9/1/2023 Partial Approval AMY COLIN
PLUMBING-Rough 9/1/2023 Approved AMY COLIN
Shower Pan 9/1/2023 Approved AMY COLIN
ELECTRICAL-Rough 9/12/2023 Approved AMY COLIN
Insulation 9/12/2023 Approved AMY COLIN
Drywall Nailing 10/4/2023 Approved AMY COLIN
ELECTRICAL-Rough 10/4/2023 Approved AMY COLIN
Green Building Rough 10/4/2023 Approved AMY COLIN
HVAC-Rough 10/4/2023 Approved AMY COLIN
Interior/Exterior Lathing 10/4/2023 Approved AMY COLIN
Interior/Exterior Lathing 10/27/2023 Approved AMY COLIN
Final 12/20/2023 OK to Issue CofO AMY COLIN
Footing/Foundation/Slab 12/20/2023 Approved AMY COLIN
Green Building Final 12/20/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Approved AMY COLIN
Smoke Detectors 12/20/2023 Approved AMY COLIN
Special/Order Compliance 1/5/2024 Corrections Issued AMY COLIN
Final 3/27/2024 OK to Issue CofO LILIANA PORTILLO
Special/Order Compliance 3/27/2024 Approved LILIANA PORTILLO