1944 S HOBART BLVD 90018
Certificate Information: 1944 S HOBART BLVD 90018
- Application / Permit
- 21014-10000-01493
- Plan Check / Job No.
- B21LA05617
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-story addition to existing garage and convert is to accessory dwelling unit (ADU).
- Permit Issued
- Issued on 10/4/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | TU HUA |
| Corrections Issued | 4/21/2021 | TU HUA |
| Quality Review Completed | 4/21/2021 | WING SUEN |
| Applicant returned to address corrections | 5/21/2021 | TU HUA |
| Plan Check Approved | 9/30/2021 | TU HUA |
| Issued | 10/4/2021 | APPLICANT |
| Building Plans Picked Up | 10/4/2021 | APPLICANT |
| CofO in Progress | 9/30/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 10/29/2022 | DEROLD HAUFF |
| CofO Issued | 10/29/2022 | DEROLD HAUFF |
| Permit Finaled | 10/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 4/7/2021 | DEEPEAKA DHALIWAL |
| ZA Case | Cleared | 4/20/2021 | DEEPEAKA DHALIWAL |
| CPC | Cleared | 4/30/2021 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 4/30/2021 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 4/30/2021 | DENZEL HENDERSON |
| ZI | Cleared | 4/30/2021 | DENZEL HENDERSON |
| Address approval | Cleared | 7/30/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/3/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 8/11/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/23/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 10/19/2021 | Partial Approval | COREY HUPP |
| Footing/Foundation/Slab | 10/26/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 10/26/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 10/26/2021 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 12/10/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 12/10/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 12/10/2021 | Approved | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 12/13/2021 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/11/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 1/11/2022 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Rough | 1/20/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 1/20/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/20/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/22/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 1/22/2022 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 1/22/2022 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 1/22/2022 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/22/2022 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Green Building Rough | 1/22/2022 | Off-Hour Fees Due | |
| HVAC-Rough | 1/22/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/22/2022 | Off-Hour Fees Due | |
| PLUMBING-Rough | 1/22/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/22/2022 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 1/31/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 1/31/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/31/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 2/2/2022 | Conditional Approval | KATHRYN BUTTERWORTH |
| Insulation | 2/3/2022 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 2/9/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/9/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/17/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 7/14/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 7/14/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 7/14/2022 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Final | 7/14/2022 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 7/14/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/26/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 8/26/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 8/26/2022 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 8/26/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 9/7/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 9/29/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Service/Power Release | 9/29/2022 | Approved | KATHRYN BUTTERWORTH |