2238 S BEVERLY DR 90034
Certificate Information: 2238 S BEVERLY DR 90034
- Application / Permit
- 21014-10000-01477
- Plan Check / Job No.
- B21LA05582
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to existing 2-story single family dwelling.
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | TU HUA |
| Corrections Issued | 4/28/2021 | TU HUA |
| Quality Review Completed | 5/6/2021 | WING SUEN |
| Building Plans Picked Up | 5/10/2021 | APPLICANT |
| Applicant returned to address corrections | 9/9/2021 | TU HUA |
| Applicant returned to address corrections | 6/3/2022 | TU HUA |
| Plan Check Approved | 6/10/2022 | TU HUA |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 11/30/2023 | JESUS PINEDA |
| Permit Finaled | 12/7/2023 | DANIEL ORRANTE |
| CofO Issued | 12/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/9/2021 | YVAINNE GALSIM |
| CPC | Cleared | 3/2/2022 | RICHARD REASER |
| CPC | Cleared | 3/2/2022 | RICHARD REASER |
| Roof/Waste drainage to street | Cleared | 3/5/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 4/2/2022 | JOSE HERNANDEZ |
| Abandoned oil well | Cleared | 5/7/2022 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 5/13/2022 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 6/3/2022 | TU HUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | PO BOX 7112 NORTHRIDGE, CA 91327 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 7/26/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/29/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/2/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 8/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/1/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/1/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/9/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/3/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/4/2023 | Partial Approval | JOHNNY MIRANDA |
| Shower Pan | 1/4/2023 | Approved | JOHNNY MIRANDA |
| Wood Frame | 1/5/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 1/6/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/9/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 1/9/2023 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 1/9/2023 | Approved | OGANES TARAKHCHYAN |
| Insulation | 1/10/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 1/12/2023 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/20/2023 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/10/2023 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/16/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 2/22/2023 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/10/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 5/10/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| Footing/Foundation/Slab | 5/10/2023 | Approved | CLAYTON GRAHAM |
| Green Building Final | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| METHANE-Barrier | 5/10/2023 | Approved | CLAYTON GRAHAM |
| METHANE-Subgrade | 5/10/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 5/10/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 5/10/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 5/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 5/17/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Smoke Detectors | 5/17/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Final | 5/24/2023 | Approved | CLAYTON GRAHAM |
| Final | 5/24/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 5/24/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 5/24/2023 | Approved | CLAYTON GRAHAM |
| Final | 9/21/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Final | 10/27/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Final | 11/30/2023 | OK to Issue CofO | JESUS PINEDA |