2713 S BARRINGTON AVE 90064

Certificate Information: 2713 S BARRINGTON AVE 90064

Application / Permit
21014-10000-01463
Plan Check / Job No.
B21LA05544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AN EXISTING SINGLE FAMILY DWELLING AT THE FRONT AND REAR, EXTERIOR ALTERATIONS TO CHANGE ROOF LAYOUT, INTERIOR ALTERATION TO CHANGE FLOOR LAY OUT (NO CHANGE IN HEIGHT, OR PARKING) SEE COMMENTS 1 OF 2
Permit Issued
Issued on 1/6/2022
Issuing Office
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 MINA HABIB
Corrections Issued 5/13/2021 MINA HABIB
Quality Review Completed 5/14/2021 FARUK SEZER
Building Plans Picked Up 5/19/2021 APPLICANT
Applicant returned to address corrections 11/2/2021 MINA HABIB
Applicant returned to address corrections 11/8/2021 MINA HABIB
Applicant returned to address corrections 11/9/2021 MINA HABIB
Applicant returned to address corrections 12/17/2021 MINA HABIB
Applicant returned to address corrections 12/22/2021 MINA HABIB
Plan Check Approved 12/27/2021 MINA HABIB
Issued 1/6/2022 APPLICANT
CofO in Progress 11/9/2022 JOHNNY MIRANDA
Permit Finaled 11/18/2022 DANIEL ORRANTE
CofO Issued 11/18/2022 DANIEL ORRANTE
Permit Finaled 11/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/8/2021 ANTHONY MAINEZ
Watercourse Cleared 6/16/2021 ANTHONY MAINEZ
Low Impact Development Cleared 9/15/2021 SUNG JOON WON
Specific Plan Cleared 9/16/2021 PEDRO AYALA
Roof/Waste drainage to street Cleared 10/4/2021 ANTHONY MAINEZ
Green Code Cleared 12/22/2021 MINA HABIB

Contact Information

Contractor Pure Builders Inc; Lic. No.: 757470-B 23966 CRAFTSMAN RD      CALABASAS, CA 91302
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/13/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Conditional Approval JOHNNY MIRANDA
ELECTRICAL-Rough 6/1/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/2/2022 Approved OGANES TARAKHCHYAN
FLOOD-Proofing Certificate 6/9/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 6/9/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 6/14/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 6/14/2022 Approved JOHNNY MIRANDA
Insulation 6/21/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/21/2022 Partial Approval JOHNNY MIRANDA
Shower Pan 6/21/2022 Approved JOHNNY MIRANDA
Drywall Nailing 6/29/2022 Approved JOHNNY MIRANDA
Green Building Rough 6/29/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/29/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/29/2022 Approved JOHNNY MIRANDA
Underground Mechanical 6/29/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 9/20/2022 Approved JOHN KIDWELL
Gas Test 9/20/2022 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 9/20/2022 Approved JOHN KIDWELL
PLUMBING-Final 9/20/2022 Conditional Approval JOHN KIDWELL
BUILDING-Rough-Frame 10/26/2022 Approved JOHNNY MIRANDA
Final 10/26/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 10/26/2022 Approved JOHNNY MIRANDA
Gas Test 10/26/2022 Approved JOHNNY MIRANDA
Green Building Final 10/26/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 10/26/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 10/26/2022 Approved JOHNNY MIRANDA
Final 11/1/2022 Conditional Approval JOHNNY MIRANDA