14470 W POLK ST 91342
Certificate Information: 14470 W POLK ST 91342
- Application / Permit
- 21014-10000-01456
- Plan Check / Job No.
- B21LA05504
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) Garage into ADU and add 5'7" x 9' bathroom
- Permit Issued
- Issued on 2/1/2022
- Issuing Office
- Current Status
- Issued on 2/1/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2021 | HERNAN ARREOLA |
| Corrections Issued | 3/29/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/8/2021 | HERNAN ARREOLA |
| Plan Check Approved | 12/4/2021 | HERNAN ARREOLA |
| Issued | 2/1/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 6/18/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/29/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/15/2022 | Partial Inspection | MICHEL ABAJAN |
| Pre-Inspection | 6/22/2022 | Approved | JASON BRANNON |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Partial Inspection | JASON BRANNON |
| Footing/Foundation/Slab | 8/11/2022 | No Access for Inspection | JASON BRANNON |
| Footing/Foundation/Slab | 8/17/2022 | Approved | JASON BRANNON |
| ELECTRICAL-Rough | 10/28/2022 | Not Ready for Inspection | JASON BRANNON |
| Insulation | 10/28/2022 | Not Ready for Inspection | JASON BRANNON |
| PLUMBING-Rough | 10/28/2022 | Not Ready for Inspection | JASON BRANNON |
| Shower Pan | 10/28/2022 | Not Ready for Inspection | JASON BRANNON |
| Wood Frame | 10/28/2022 | Not Ready for Inspection | JASON BRANNON |
| ELECTRICAL-Rough | 11/7/2022 | Approved | JASON BRANNON |
| Insulation | 11/7/2022 | Partial Inspection | JASON BRANNON |
| PLUMBING-Rough | 11/7/2022 | Approved | JASON BRANNON |
| Shower Pan | 11/7/2022 | Approved | JASON BRANNON |
| Wood Frame | 11/7/2022 | Approved | JASON BRANNON |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Approved | EMIL ALEXANDRIAN |
| Drywall Nailing | 11/17/2022 | Approved | JASON BRANNON |
| Green Building Rough | 11/17/2022 | Approved | JASON BRANNON |
| Interior/Exterior Lathing | 11/29/2022 | Approved | JASON BRANNON |
| Interior/Exterior Lathing | 12/15/2022 | Approved | JASON BRANNON |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Not Ready | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 12/22/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 12/22/2023 | Corrections Issued | AGUSTIN ALVAREZMORALES |
| Green Building Final | 12/22/2023 | Approved | AGUSTIN ALVAREZMORALES |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Not Ready | AGUSTIN ALVAREZMORALES |
| Smoke Detectors | 12/22/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 6/10/2024 | Conditional Approval | MARK VAN SLOOTEN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Approved | MARK VAN SLOOTEN |