1629 S HI POINT ST 90035

Certificate Information: 1629 S HI POINT ST 90035

Application / Permit
21014-10000-01455
Plan Check / Job No.
B21LA05503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW ATTACHED ACCESSORY DWELLING UNIT TO (E) DETACHED GARAGE AT REAR PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/16/2021
Issuing Office
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/6/2021 KEVIN MORALES
Corrections Issued 4/7/2021 KEVIN MORALES
Applicant returned to address corrections 6/1/2021 KEVIN MORALES
Plan Check Approved 10/13/2021 KEVIN MORALES
Issued 11/16/2021 APPLICANT
CofO in Progress 11/20/2023 STUART CHAPMAN
Permit Finaled 12/27/2023 DEROLD HAUFF
CofO Issued 12/27/2023 DEROLD HAUFF
Permit Finaled 12/27/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/19/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 7/19/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 7/21/2021 THOMAS LANG
Sewer availability Cleared 10/13/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/23/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/23/2021 Corrections Issued JOSE AVILA
METHANE-Barrier 11/23/2021 Approved JOSE AVILA
METHANE-Subgrade 11/23/2021 Approved JOSE AVILA
Special/Order Compliance 1/10/2022 No Violation (special insp) SHAVONNE ESPINOZA
Footing/Foundation/Slab 5/10/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 9/21/2022 Partial Approval JOSE AVILA
Sewer 9/21/2022 Approved JOSE AVILA
Deputy Drilled-In Anchors 11/7/2022 Conditional Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/27/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 1/27/2023 Corrections Issued JOSE AVILA
PLUMBING-Rough 1/27/2023 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 1/30/2023 Approved JOSE AVILA
Wood Frame 3/15/2023 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 3/31/2023 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval JOSE AVILA
Rough-Elec/Plmb/HVAC 4/13/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 7/10/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/10/2023 Partial Approval JOSE AVILA
ELECTRICAL-Rough 7/28/2023 Approved MICHAEL LEWIS
HVAC-Rough 7/28/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 7/28/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 7/28/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/4/2023 Partial Approval JOSE AVILA
HVAC-Rough 8/4/2023 Approved JOSE AVILA
METHANE-Rough 8/4/2023 Approved JOSE AVILA
Green Building Rough 8/11/2023 Approved JOSE AVILA
Insulation 8/11/2023 Approved JOSE AVILA
Shower Pan 8/11/2023 Approved JOSE AVILA
Drywall Nailing 8/18/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 11/8/2023 Approved JOSE AVILA
Final 11/8/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/8/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 11/8/2023 Approved JOSE AVILA
ELECTRICAL-Final 11/17/2023 Approved STUART CHAPMAN
Final 11/17/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 11/17/2023 Approved STUART CHAPMAN
PLUMBING-Final 11/17/2023 Approved STUART CHAPMAN