9306 N STANWIN AVE 91331
Certificate Information: 9306 N STANWIN AVE 91331
- Application / Permit
- 21014-10000-01423
- Plan Check / Job No.
- B21LA05402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | KEVIN MORALES |
| Corrections Issued | 3/25/2021 | KEVIN MORALES |
| Plan Check Approved | 6/29/2021 | KEVIN MORALES |
| Issued | 7/6/2021 | APPLICANT |
| CofO in Progress | 12/22/2021 | MICHEL ABAJAN |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
| CofO Issued | 1/22/2022 | MICHAEL SMITH |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/26/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 5/30/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/8/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/18/2021 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/31/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/16/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/16/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/16/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/16/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/16/2021 | Approved | MICHEL ABAJAN |
| Insulation | 9/21/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/21/2021 | Approved | MICHEL ABAJAN |
| Shower Pan | 9/21/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/23/2021 | Approved | MICHEL ABAJAN |
| Gas Test | 9/23/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/23/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/17/2021 | Approved | MICHEL ABAJAN |
| Final | 11/17/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/17/2021 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/17/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/17/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/17/2021 | Approved | MICHEL ABAJAN |
| Final | 12/22/2021 | OK to Issue CofO | MICHEL ABAJAN |