3529 S OCEAN VIEW AVE 90066

Certificate Information: 3529 S OCEAN VIEW AVE 90066

Application / Permit
21014-10000-01421
Plan Check / Job No.
B21LA05400
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU addition. Convert existing 468 s.f. detached garage plus 240sq. ft addition to ADU per Ordinance & LAMC 12.22 A 33(c)&(d).All work per Engineer Design.
Permit Issued
Issued on 9/21/2022
Issuing Office
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 4/5/2021 ZAW HAN
Corrections Issued 4/5/2021 ZAW HAN
Plan Check Approved 9/17/2022 ZAW HAN
Issued 9/21/2022 APPLICANT
CofO in Progress 8/4/2023 DAVID FEILER
Permit Finaled 8/10/2023 DANIEL ORRANTE
CofO Issued 8/10/2023 DANIEL ORRANTE
Permit Finaled 8/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/20/2021 NIKTA MOUSAVI
Specific Plan Cleared 9/28/2021 KEVIN ARUCAN
CPC Cleared 11/19/2021 MAXFIELD VERMY
CPC Cleared 11/19/2021 MAXFIELD VERMY
Low Impact Development Cleared 11/19/2021 JONATAN VELASQUEZ
Eng Process Fee Ord 176,300 Cleared 12/2/2021 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 9/6/2022 CATHERINE ADROVER
Sewer availability Cleared 9/6/2022 CATHERINE ADROVER

Contact Information

Contractor J C C Golden Star Construction Inc; Lic. No.: 933982-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780
Engineer Barakat,, Fouad Chafic; Lic. No.: NA67449       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/7/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 10/13/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Partial Approval HERBERT GIRON
PLUMBING-Rough 10/19/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 11/22/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 11/22/2022 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval JOHNNY MIRANDA
HVAC-Rough 11/22/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 11/22/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 12/6/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 12/6/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Approved JOHNNY MIRANDA
Green Building Rough 12/6/2022 Approved JOHNNY MIRANDA
HVAC-Rough 12/6/2022 Approved JOHNNY MIRANDA
Insulation 12/6/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/6/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 12/6/2022 Approved JOHNNY MIRANDA
Drywall Nailing 12/13/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/13/2022 Approved JOHNNY MIRANDA
Shower Pan 12/13/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 2/2/2023 Corrections Issued JOHNNY MIRANDA
Final 2/2/2023 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 2/2/2023 Approved JOHNNY MIRANDA
Green Building Final 2/2/2023 Approved JOHNNY MIRANDA
HVAC-Final 2/2/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 2/2/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 2/2/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 2/7/2023 Approved JOHNNY MIRANDA
HVAC-Final 2/7/2023 Approved JOHNNY MIRANDA
Final 5/11/2023 Corrections Issued JOHNNY MIRANDA
Final 8/4/2023 OK to Issue CofO JESUS PINEDA