4274 S GRAND VIEW BLVD 90066

Certificate Information: 4274 S GRAND VIEW BLVD 90066

Application / Permit
21014-10000-01418
Plan Check / Job No.
B21LA05388
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED GROUND FLOOR AND 2ND STORY ADDITION TO (E) 1 STORY SFD.
Permit Issued
Issued on 8/11/2021
Issuing Office
Current Status
CofO Issued on 2/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 KHEDER ALRAZAA
Corrections Issued 4/23/2021 KHEDER ALRAZAA
Quality Review Completed 4/26/2021 ALLEN MANALANSAN
Plan Check Approved 7/28/2021 KHEDER ALRAZAA
Issued 8/11/2021 APPLICANT
Building Plans Picked Up 8/19/2021 APPLICANT
CofO in Progress 2/14/2024 JESUS RODRIGUEZ
Permit Finaled 2/26/2024 DANIEL ORRANTE
CofO Issued 2/26/2024 DANIEL ORRANTE
Permit Finaled 2/26/2024 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 5/18/2021 PEDRO AYALA
Low Impact Development Cleared 6/30/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/2/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/7/2021 DINAH GARIN
Sewer availability Cleared 7/7/2021 DINAH GARIN

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/1/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 9/10/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 12/27/2021 Partial Approval ENRIQUE MIRELES
Green Building Rough 12/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 12/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 1/27/2022 Approved ENRIQUE MIRELES
Insulation 2/18/2022 Approved ENRIQUE MIRELES
Shower Pan 2/25/2022 Approved ENRIQUE MIRELES
Drywall Nailing 3/10/2022 Approved ENRIQUE MIRELES
Green Building Rough 3/10/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/10/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/3/2022 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Final 10/6/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 10/12/2022 SGSOV Not Ready JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/4/2022 Approved JESUS RODRIGUEZ
Final 11/4/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 11/4/2022 Approved JESUS RODRIGUEZ
HVAC-Final 11/4/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 11/4/2022 Corrections Issued JESUS RODRIGUEZ
Final 12/12/2022 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 12/12/2022 Approved JESUS RODRIGUEZ
Final 7/13/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 11/14/2023 Approved JESUS RODRIGUEZ
Final 11/14/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 11/14/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 11/14/2023 Approved JESUS RODRIGUEZ
Final 2/14/2024 OK to Issue CofO JESUS RODRIGUEZ