5141 E WADENA ST 90032

Certificate Information: 5141 E WADENA ST 90032

Application / Permit
21014-10000-01416
Plan Check / Job No.
B21LA05376
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED GROUND FLOOR ADDITION AND SECOND STORY ADDITION TO EXISTING DETACHED GARAGE. 2-CAR GARAGE TO REMAIN, GROUND FLOOR ADDITION WILL CREATE A COVERED PATIO AND SECOND FLOOR WILL BE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 6/16/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 MICHAEL LOPEZ
Corrections Issued 4/22/2021 MICHAEL LOPEZ
Quality Review Completed 4/29/2021 KEN GILL
Building Plans Picked Up 4/30/2021 APPLICANT
Applicant returned to address corrections 6/13/2022 MICHAEL LOPEZ
Plan Check Approved 6/15/2022 MICHAEL LOPEZ
Issued 6/16/2022 APPLICANT
CofO in Progress 7/19/2023 AMY COLIN
Permit Finaled 8/6/2023 DEROLD HAUFF
CofO Issued 8/6/2023 DEROLD HAUFF
Permit Finaled 8/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/14/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 8/14/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/25/2021 STEVE MELGAR
Sewer availability Cleared 8/25/2021 STEVE MELGAR
Hydrant and Access approval Cleared 10/20/2021 MATTHEW CRAIG
"D" conditions Cleared 4/26/2022 RUBEN VASQUEZ
"Q" conditions Cleared 4/26/2022 RUBEN VASQUEZ
ZI Cleared 4/26/2022 RUBEN VASQUEZ
Low Impact Development Cleared 4/27/2022 JORGE MEJIA LEMUS
Grading Pre-Inspection Cleared 5/6/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 5/14/2022 JEANETTE VONG
GPI Written Notices Cleared 6/15/2022 ROBERT HUGHES

Contact Information

Contractor Owner-Builder       ,
Engineer Alatorre-Y-Barroso,, Alejandro Javier; Lic. No.: C32761 7411 FLORENCE AVE      DOWNEY, CA 90240
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2022 Approved AMY COLIN
Footing/Foundation/Slab 8/22/2022 Approved AMY COLIN
Underground Mechanical 8/24/2022 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Approved AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Partial Approval AMY COLIN
Interior/Exterior Lathing 11/3/2022 Corrections Issued AMY COLIN
ELECTRICAL-Rough 11/17/2022 Approved AMY COLIN
HVAC-Rough 11/17/2022 Approved AMY COLIN
Interior/Exterior Lathing 11/17/2022 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 11/17/2022 Approved AMY COLIN
Insulation 11/29/2022 Not Ready for Inspection AMY COLIN
Insulation 12/7/2022 Not Ready for Inspection AMY COLIN
Interior/Exterior Lathing 12/7/2022 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 12/13/2022 Corrections Issued AMY COLIN
Insulation 12/13/2022 Approved AMY COLIN
Interior/Exterior Lathing 12/13/2022 Partial Approval AMY COLIN
BUILDING-Rough-Frame 12/19/2022 Approved AMY COLIN
Drywall Nailing 12/19/2022 Approved AMY COLIN
Green Building Rough 12/19/2022 Approved AMY COLIN
Service/Power Release 3/24/2023 Corrections Issued AMY COLIN
Final 5/15/2023 Corrections Issued AMY COLIN
Green Building Final 5/15/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved AMY COLIN
Smoke Detectors 5/15/2023 Approved AMY COLIN
Final 6/15/2023 Corrections Issued AMY COLIN
Final 6/22/2023 Corrections Issued AMY COLIN
Final 7/5/2023 Conditional Approval RUBEN SALAS
Final 7/19/2023 OK to Issue CofO AMY COLIN