16578 W VIA FLORESTA 90272
Certificate Information: 16578 W VIA FLORESTA 90272
- Application / Permit
- 21014-10000-01412
- Plan Check / Job No.
- B21LA05364
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 story ADDITION AND REMODEL OF EXISTING SFD
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 12/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 4/15/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/22/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
| Plan Check Approved | 8/19/2021 | ARSALAN SHABESTARI |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 12/7/2021 | ANDREW NAVE |
| Permit Finaled | 12/23/2021 | DANIEL ORRANTE |
| CofO Issued | 12/23/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/23/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2021 | RAYMOND MUGAMBWA |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | RAYMOND MUGAMBWA |
| Sewer availability | Cleared | 5/17/2021 | RAYMOND MUGAMBWA |
| Tract Map conditions | Cleared | 5/20/2021 | LOUIS ORTEGA |
| Coastal Zone | Cleared | 7/15/2021 | LOUIS ORTEGA |
| ZI | Cleared | 7/15/2021 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 8/19/2021 | ARSALAN SHABESTARI |
Contact Information
| Contractor | N A N D C O Llc; Lic. No.: 1044615-B | 4836 FULTON AVE SHERMAN OAKS, CA 91423 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/14/2021 | Approved | ANDREW NAVE |
| Structural Steel Frame | 10/14/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 10/28/2021 | Partial Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 10/28/2021 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Rough | 11/2/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/2/2021 | Partial Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 11/3/2021 | Approved | ANDREW NAVE |
| Insulation | 11/5/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 11/8/2021 | Conditional Approval | ANDREW NAVE |
| Insulation | 11/9/2021 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/15/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 11/15/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 11/15/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/18/2021 | Approved | DANIEL ORRANTE |
| Final | 12/2/2021 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 12/2/2021 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 12/2/2021 | Corrections Issued | ANDREW NAVE |
| Final | 12/7/2021 | OK to Issue CofO | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 12/7/2021 | Approved | ANDREW NAVE |