751 S MISSION ROAD 90023

Certificate Information: 751 S MISSION ROAD 90023

Application / Permit
21014-10000-01408
Plan Check / Job No.
B21LA05352
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(21) Motion Picture Production
Work Description
REMODEL OF (E) ONE STORY, TYPE IIIA, WAREHOUSE BUILDING TO THREE STORY, TYPE IIIA, MOTION PICTURE PRODUCTION & OFFICES. SITE IMPORVEMNT & PARKING RESTRIPING.
Permit Issued
Issued on 10/12/2021
Issuing Office
Current Status
CofO Issued on 5/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 KESETE HAREGOT
Building Plans Picked Up 4/5/2021 APPLICANT
Corrections Issued 4/16/2021 KESETE HAREGOT
Quality Review Completed 4/16/2021 FARUK SEZER
Green Plans Picked Up 8/11/2021 APPLICANT
Applicant returned to address corrections 9/29/2021 KESETE HAREGOT
Plan Check Approved 10/12/2021 KESETE HAREGOT
Issued 10/12/2021 APPLICANT
TCO Issued (Expire Date: 12-05-2023) 6/8/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 06-01-2024) 12/4/2023 ERNESTO CORRAL
CofO in Progress 2/6/2024 ADAM BURGESS
TCO Issued (Expire Date: 11-26-2024) 5/30/2024 RAFAEL ESPINOZA
TCO Issued (Expire Date: 05-20-2025) 11/21/2024 RAFAEL ESPINOZA
CofO Issued 5/20/2025 RAFAEL ESPINOZA
Permit Finaled 5/20/2025 RAFAEL ESPINOZA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/10/2021 WALLIE JONG
Address approval Cleared 5/12/2021 WALLIE JONG
Hydrant and Access approval Cleared 6/18/2021 JOHN CONNEALLY
Internal circulation Cleared 6/22/2021 TAIMOUR TANAVOLI
Sewer availability Cleared 6/28/2021 WALLIE JONG
Historic Resource Verification Cleared 7/12/2021 MICAELA TORRES-GIL
Metro Rail approval Cleared 8/2/2021 MTA APPROVED
Redevelopment Project Area Cleared 8/5/2021 GRACIELA ACOSTA
Green Code Cleared 8/9/2021 AARON COSTA
Construction near power lines Cleared 8/30/2021 RIDWAN HARDY
Clean Up Green Up Cleared 9/2/2021 TERRI OSBORNE
Automotive Use Cleared 9/7/2021 TERRI OSBORNE
Low Impact Development Cleared 9/8/2021 IDA MEISAMI-FARD
Motion picture studio Cleared 9/9/2021 VIDAL GARCIA
DAS Clearance Cleared 9/16/2021 SHINE LIN
Drainage to Storm Drain Cleared 10/6/2021 THAN WIN
Highway dedication Cleared 10/6/2021 THAN WIN

Contact Information

Architect Sullivan,, Scott Bernard; Lic. No.: C33139 828 11TH STREET # 5      SANTA MONICA, CA 90403
Contractor Ozair Construction & Design Inc; Lic. No.: 992682-B 2228 LAUREL CANYON BLVD      LOS ANGELES, CA 90045
Engineer Alajov,, John J; Lic. No.: C56393 5143 TYRONE AVE      SHERMAN OAKS, CA 91423
Engineer Cosentino,, Joseph; Lic. No.: C53176 820 ISABELLA      MONTEREY PARK, CA 91754

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/18/2021 Not Ready for Inspection MARK FERRARI
Piling/Pier/Caisson 10/20/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 10/25/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/1/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 12/1/2021 Partial Approval BRUCE CAMPBELL
Pre-Inspection 12/15/2021 Not Ready for Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 12/16/2021 Not Ready for Inspection MARK FERRARI
Deputy Drilled-In Anchors 12/17/2021 Approved MARK FERRARI
Footing/Foundation/Slab 12/17/2021 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 1/18/2022 No Result Entered RONALD PACHECO
Footing/Foundation/Slab 1/19/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 1/24/2022 Partial Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 1/25/2022 Conditional Approval MARK FERRARI
Pre-Inspection 1/25/2022 Partial Approval MARK FERRARI
Deputy Steel/Welding 1/26/2022 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 1/27/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 1/27/2022 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 2/3/2022 Conditional Approval MARK FERRARI
Reinforced Concrete Frame 2/11/2022 Not Ready for Inspection MARK FERRARI
Deputy Shotcrete 2/14/2022 Conditional Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 2/23/2022 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 3/3/2022 Corrections Issued MARK FERRARI
Deputy Steel/Welding 3/7/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 3/8/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 3/15/2022 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 3/15/2022 Partial Approval MARK FERRARI
Deputy Steel/Welding 3/16/2022 Conditional Approval MARK FERRARI
Reinforced Concrete Frame 3/17/2022 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 3/22/2022 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 3/24/2022 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 4/4/2022 Corrections Issued MARK FERRARI
Deputy Drilled-In Anchors 4/6/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 4/6/2022 Conditional Approval MARK FERRARI
Reinforced Concrete Frame 4/6/2022 Partial Approval MARK FERRARI
Deputy Steel/Welding 4/7/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 4/12/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 4/14/2022 Order to Comply Issued BRUCE CAMPBELL
Deputy Steel/Welding 4/15/2022 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 4/15/2022 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 4/21/2022 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 4/25/2022 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 4/28/2022 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 5/12/2022 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 5/17/2022 Partial Approval MARK FERRARI
Footing/Foundation/Slab 6/6/2022 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Partial Approval MARK FERRARI
Special/Order Compliance 6/24/2022 Corrections Issued MARK FERRARI
Wood Frame 6/24/2022 Partial Approval MARK FERRARI
Deputy Steel/Welding 7/1/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 7/5/2022 Corrections Issued BRUCE CAMPBELL
Deputy Steel/Welding 7/6/2022 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 7/7/2022 Conditional Approval ERNESTO CORRAL
Deputy Drilled-In Anchors 7/15/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Drilled-In Anchors 7/18/2022 Conditional Approval WINSTON DUNNING
Deputy Wood Construction 7/18/2022 Conditional Approval WINSTON DUNNING
Deputy Drilled-In Anchors 7/19/2022 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 7/20/2022 Conditional Approval MARK FERRARI
Deputy Steel/Welding 7/20/2022 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 7/20/2022 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 7/26/2022 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 8/9/2022 Conditional Approval MARK FERRARI
Deputy Wood Construction 8/10/2022 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Corrections Issued MARK FERRARI
Deputy Drilled-In Anchors 8/12/2022 Conditional Approval ERNESTO CORRAL
Deputy Wood Construction 8/15/2022 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Not Ready for Inspection MARK FERRARI
Deputy Wood Construction 8/16/2022 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 8/22/2022 Partial Inspection MARK FERRARI
Deputy Wood Construction 8/26/2022 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Corrections Issued MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Partial Approval NICK DANERI
Interior/Exterior Lathing 9/19/2022 Partial Inspection MARK FERRARI
Reinforced Concrete Frame 9/19/2022 Partial Approval MARK FERRARI
Interior/Exterior Lathing 9/20/2022 Partial Approval MARK FERRARI
Insulation 9/22/2022 Not Ready for Inspection MARK FERRARI
Interior/Exterior Lathing 9/22/2022 Not Ready for Inspection MARK FERRARI
Interior/Exterior Lathing 9/26/2022 Partial Approval MARK FERRARI
Insulation 9/27/2022 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 10/5/2022 Partial Approval MARK FERRARI
Special/Order Compliance 10/5/2022 Corrections Issued MARK FERRARI
Deputy Drilled-In Anchors 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 10/18/2022 Partial Approval MARK FERRARI
Insulation 10/25/2022 Not Ready for Inspection MARK FERRARI
Deputy Steel/Welding 10/27/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 10/31/2022 Not Ready for Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Not Ready for Inspection MARK FERRARI
Insulation 11/14/2022 Corrections Issued MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Inspection MARK FERRARI
Insulation 11/16/2022 Partial Approval MARK FERRARI
Drywall Nailing 11/18/2022 Partial Approval MARK FERRARI
Insulation 11/18/2022 Partial Approval MARK FERRARI
Drywall Nailing 11/21/2022 Partial Approval MARK FERRARI
Insulation 11/21/2022 Order to Comply Issued MARK FERRARI
Drywall Nailing 11/23/2022 Partial Approval MARK FERRARI
Insulation 11/23/2022 Partial Approval MARK FERRARI
Drywall Nailing 11/28/2022 Partial Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Inspection MARK FERRARI
Insulation 11/28/2022 Partial Approval MARK FERRARI
Drywall Nailing 11/30/2022 Partial Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Partial Approval MARK FERRARI
Drywall Nailing 12/2/2022 Partial Approval MARK FERRARI
Deputy Steel/Welding 12/9/2022 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 12/9/2022 Partial Approval MARK FERRARI
Insulation 12/9/2022 Partial Approval MARK FERRARI
Deputy Fireproofing 12/12/2022 Conditional Approval MICHAEL ROSENBERG
Pre-Inspection 12/13/2022 Partial Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 12/30/2022 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 1/4/2023 Approved RAFAEL ESPINOZA
Masonry Wall/Backfill 1/9/2023 Partial Approval RAFAEL ESPINOZA
Deputy Fireproofing 1/12/2023 Conditional Approval RAFAEL ESPINOZA
Deputy Fireproofing 1/13/2023 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 1/30/2023 Not Ready for Inspection RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 1/31/2023 Partial Approval RAFAEL ESPINOZA
Pre-Inspection 2/16/2023 Partial Inspection RAFAEL ESPINOZA
Final 3/23/2023 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 3/23/2023 Partial Inspection GREGORY POMISH
Green Building Final 3/23/2023 Approved GREGORY POMISH
Green Building Rough 3/23/2023 Approved GREGORY POMISH
Reinforced Masonry Frame 3/23/2023 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 3/23/2023 SGSOV Approved GREGORY POMISH
Smoke Detectors 3/23/2023 Approved GREGORY POMISH
Final 3/28/2023 No Access for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/28/2023 No Access for Inspection EDWIN GREGORYONA
Final 4/3/2023 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 4/3/2023 Approved RAFAEL ESPINOZA
Final 5/19/2023 Conditional Approval GREGORY POMISH
Special/Order Compliance 11/8/2023 Approved RAFAEL ESPINOZA
Special/Order Compliance 5/7/2024 Approved RAFAEL ESPINOZA
Special/Order Compliance 5/30/2024 Approved RAFAEL ESPINOZA
Special/Order Compliance 10/29/2024 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 4/22/2025 Approved RAFAEL ESPINOZA