1659 S CORNING ST 90035

Certificate Information: 1659 S CORNING ST 90035

Application / Permit
21014-10000-01390
Plan Check / Job No.
B21LA05312
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW PRE-FABRICATED STATE APPROVED ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 7/28/2021
Issuing Office
Current Status
CofO Corrected on 12/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RAHEL BEYENE
Corrections Issued 3/26/2021 RAHEL BEYENE
Plan Check Approved 7/15/2021 RICARDO RAMIREZ
Issued 7/28/2021 APPLICANT
Building Plans Picked Up 7/29/2021 APPLICANT
CofO in Progress 10/1/2021 EVAN COOPER
CofO Issued-Status Void 11/17/2021 KENNETH NAGLE
Permit Finaled-Status Void 11/17/2021 KENNETH NAGLE
Re-Activate Permit 12/2/2021 DANIEL ORRANTE
Permit Finaled 12/2/2021 DANIEL ORRANTE
CofO Corrected 12/2/2021 DANIEL ORRANTE
Permit Finaled 12/2/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/8/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 4/8/2021 RENZ SORIANO
Address approval Cleared 4/16/2021 RENZ SORIANO
Sewer availability Cleared 4/16/2021 RENZ SORIANO
Hydrant and Access approval Cleared 6/15/2021 KURT CORRAL

Contact Information

Contractor Cover Technologies Inc; Lic. No.: 1039029-B 1219 W 135TH STREET      GARDENA, CA 90247
Engineer Nielsen,, Gregory Michael Wat; Lic. No.: S6653 4991 WESTPARK DR      VALLEY VILLAGE, CA 91601

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/7/2021 Partial Approval JUAN VALENZUELA
Underground Mechanical 8/7/2021 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/12/2021 Corrections Issued JUAN VALENZUELA
Grounding or Bonding 8/12/2021 Not Ready for Inspection JUAN VALENZUELA
Sewer 8/12/2021 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 8/13/2021 Approved JUAN VALENZUELA
METHANE-Barrier 8/13/2021 Approved JUAN VALENZUELA
METHANE-Subgrade 8/13/2021 Approved JUAN VALENZUELA
Sewer 8/17/2021 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 8/17/2021 Partial Inspection SHAVONNE ESPINOZA
Special/Order Compliance 8/19/2021 Approved JUAN VALENZUELA
Underground Mechanical 8/19/2021 Approved JUAN VALENZUELA
Deputy Drilled-In Anchors 8/30/2021 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 9/27/2021 Approved EVAN COOPER
Drywall Nailing 9/27/2021 Approved EVAN COOPER
Final 9/27/2021 Corrections Issued EVAN COOPER
Green Building Final 9/27/2021 Approved EVAN COOPER
Green Building Rough 9/27/2021 Approved EVAN COOPER
METHANE-Final 9/27/2021 Approved EVAN COOPER
METHANE-Rough 9/27/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved EVAN COOPER
Service/Power Release 9/27/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 9/27/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 9/27/2021 Approved EVAN COOPER
ELECTRICAL-Final 10/1/2021 Approved EVAN COOPER
Final 10/1/2021 OK to Issue CofO EVAN COOPER
HVAC-Final 10/1/2021 Approved EVAN COOPER
PLUMBING-Final 10/1/2021 Approved EVAN COOPER
Service/Power Release 10/1/2021 Approved EVAN COOPER