2234 S DUNSMUIR AVE 90016

Certificate Information: 2234 S DUNSMUIR AVE 90016

Application / Permit
21014-10000-01381
Plan Check / Job No.
B21LA05291
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 2-STORY ADU TO EXISTING DETACHED GARAGE PER LAMC12.22A33(c),(d)
Permit Issued
Issued on 1/10/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 SAM CHANG
Corrections Issued 5/4/2021 SAM CHANG
Quality Review Completed 5/5/2021 EUGENE BARBEAU
Building Plans Picked Up 5/27/2021 APPLICANT
Applicant returned to address corrections 9/28/2021 SAM CHANG
Plan Check Approved 4/7/2022 SAM CHANG
Plan Check Approved 1/10/2023 SAM CHANG
Issued 1/10/2023 APPLICANT
CofO in Progress 10/4/2024 ARTHUR NEGRETE
Permit Finaled 3/30/2025 DEROLD HAUFF
CofO Issued 3/30/2025 DEROLD HAUFF
Permit Finaled 3/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/2/2021 WALLIE JONG
Sewer availability Cleared 12/2/2021 WALLIE JONG
Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN
Low Impact Development Cleared 3/14/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/14/2022 WALLIE JONG
Green Code Cleared 4/7/2022 SAM CHANG

Contact Information

Contractor Lightning Construction Company; Lic. No.: 900084-B 16804 CALIFORNIA AVE      BELLFLOWER, CA 90706
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/7/2023 Not Ready for Inspection JOSE AVILA
Pre-Inspection 9/1/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 9/5/2023 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 9/7/2023 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/5/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 1/5/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Approved RONNIE MINDANAO
Green Building Rough 1/5/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 1/5/2024 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 1/5/2024 Approved RONNIE MINDANAO
Rough-Elec/Plmb/HVAC 1/16/2024 Corrections Issued RONNIE MINDANAO
Wood Frame 1/16/2024 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 2/1/2024 Approved STUART CHAPMAN
HVAC-Rough 2/1/2024 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/1/2024 Partial Approval STUART CHAPMAN
Insulation 2/8/2024 Approved STUART CHAPMAN
Drywall Nailing 2/14/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 2/14/2024 Approved RONNIE MINDANAO
Gas Test 6/20/2024 Approved ARTHUR NEGRETE
Sewer 7/1/2024 Approved ARTHUR NEGRETE
Service/Power Release 7/25/2024 Approved ARTHUR NEGRETE
Underground Mechanical 7/25/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 8/5/2024 Approved ARTHUR NEGRETE
Final 8/5/2024 Not Ready for Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 8/5/2024 Approved ARTHUR NEGRETE
Green Building Final 8/5/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 8/5/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 8/5/2024 Approved ARTHUR NEGRETE
Special/Order Compliance 8/5/2024 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Final 8/6/2024 Approved ARTHUR NEGRETE
HVAC-Final 8/6/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 8/6/2024 Approved ARTHUR NEGRETE
Final 10/3/2024 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 10/3/2024 Approved ARTHUR NEGRETE
Service/Power Release 10/3/2024 Approved ARTHUR NEGRETE