15239 W LASSEN ST 91345
Certificate Information: 15239 W LASSEN ST 91345
- Application / Permit
- 21014-10000-01377
- Plan Check / Job No.
- B21LA05274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- e-plan: Proposed second floor addition to an existing detached garage to create an Accessory Dwelling Unit per Ordinance. Scope will also include an attached patio, existing garage to remain.
- Permit Issued
- Issued on 8/24/2022
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | MICHAEL LOPEZ |
| Corrections Issued | 4/12/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 4/22/2021 | WING SUEN |
| Applicant returned to address corrections | 2/11/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/20/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 8/8/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 8/18/2022 | MICHAEL LOPEZ |
| Issued | 8/24/2022 | APPLICANT |
| CofO in Progress | 3/19/2026 | JENNIFER RABUCHIN |
| CofO Issued | 4/2/2026 | RUBEN SALAS |
| Permit Finaled | 4/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/20/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 1/22/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/24/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 8/9/2022 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/8/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 8/16/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/7/2025 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/28/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/28/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Wood Construction | 4/30/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Steel/Welding | 7/10/2025 | No Result Entered | JOHN COLEMAN |
| BUILDING-Rough-Frame | 7/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 7/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/11/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 7/11/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/17/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 7/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/17/2025 | Approved | JENNIFER RABUCHIN |
| Sewer | 7/17/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/1/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/1/2025 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 8/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/10/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 3/10/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/16/2026 | Approved | JENNIFER RABUCHIN |
| Final | 3/16/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 3/16/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/16/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/16/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 3/16/2026 | Approved | JENNIFER RABUCHIN |