3424 N DIVISION ST 90065
Certificate Information: 3424 N DIVISION ST 90065
- Application / Permit
- 21014-10000-01375
- Plan Check / Job No.
- B21LA05249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU WITH GARAGE PER LAMC 12.22 A33 C & D AND PER CITY PLANNING CASE ADM-2021-2683-ADU
- Permit Issued
- Issued on 6/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | STARR CHEN |
| Corrections Issued | 3/30/2021 | STARR CHEN |
| Applicant returned to address corrections | 5/21/2021 | STARR CHEN |
| Applicant returned to address corrections | 6/4/2021 | ZAW HAN |
| Plan Check Approved | 6/8/2021 | ZAW HAN |
| Building Plans Picked Up | 6/14/2021 | APPLICANT |
| Issued | 6/18/2021 | APPLICANT |
| CofO in Progress | 4/14/2022 | OSVALDO PARAMO |
| CofO in Progress | 4/14/2022 | OSVALDO PARAMO |
| CofO Issued | 4/25/2022 | DEROLD HAUFF |
| Permit Finaled | 4/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/1/2021 | NASHYA JENSEN |
| Address approval | Cleared | 4/5/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/13/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 5/12/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/12/2021 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 5/13/2021 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 5/21/2021 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 5/21/2021 | STARR CHEN |
Contact Information
| Contractor | N A N D C O Llc; Lic. No.: 1044615-B | 4836 FULTON AVE SHERMAN OAKS, CA 91423 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2021 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 7/13/2021 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/13/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 7/27/2021 | No Access for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 7/28/2021 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/2/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 9/7/2021 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 9/9/2021 | Conditional Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/20/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 9/20/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 9/20/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2021 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 9/29/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/4/2021 | Approved | OSVALDO PARAMO |
| Shower Pan | 10/4/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/7/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/7/2021 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 10/7/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/7/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/8/2021 | Approved | OSVALDO PARAMO |
| Insulation | 10/13/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 10/19/2021 | Approved | OSVALDO PARAMO |
| Special/Order Compliance | 11/30/2021 | Partial Inspection | SHAVONNE ESPINOZA |
| Underground Mechanical | 11/30/2021 | Approved | OSVALDO PARAMO |
| Gas Test | 12/16/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Service/Power Release | 12/16/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 2/22/2022 | Approved | OSVALDO PARAMO |
| Final | 2/22/2022 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 2/22/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 2/22/2022 | Approved | OSVALDO PARAMO |
| Gas Test | 3/15/2022 | Approved | OSVALDO PARAMO |
| Final | 3/21/2022 | OK to Issue CofO | OSVALDO PARAMO |
| Green Building Final | 3/21/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 3/21/2022 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 3/21/2022 | Approved | OSVALDO PARAMO |