2545-2545 1/2 E ZONAL AVE 90033

Certificate Information: 2545-2545 1/2 E ZONAL AVE 90033

Application / Permit
21014-10000-01363
Plan Check / Job No.
B21LA05232
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ROOM ADDITION (158) SF TO THE ADU (WORK IN PROGRESS) PERMIT #19016-10000-18782.
Permit Issued
Issued on 8/6/2021
Issuing Office
Current Status
CofO Issued on 10/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RACHEL BEYENE
Corrections Issued 3/25/2021 RACHEL BEYENE
Applicant returned to address corrections 6/4/2021 SAMUEL GONZALEZ
Plan Check Approved 7/28/2021 DANIEL SANJUAN
Issued 8/6/2021 APPLICANT
Building Plans Picked Up 8/12/2021 APPLICANT
CofO in Progress 10/4/2022 OSVALDO PARAMO
CofO in Progress 10/4/2022 OSVALDO PARAMO
Permit Finaled 10/28/2022 DEROLD HAUFF
CofO Issued 10/28/2022 DEROLD HAUFF
Permit Finaled 10/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/11/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/15/2021 RENZ SORIANO
Sewer availability Cleared 7/15/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/9/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 4/22/2022 Partial Approval OSVALDO PARAMO
Deputy Drilled-In Anchors 4/26/2022 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/3/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 5/3/2022 Approved OSVALDO PARAMO
Wood Frame 5/3/2022 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/11/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 5/18/2022 Approved OSVALDO PARAMO
Green Building Rough 5/18/2022 Approved OSVALDO PARAMO
MERV13>=Rough 5/18/2022 Approved OSVALDO PARAMO
Insulation 5/23/2022 Approved OSVALDO PARAMO
Drywall Nailing 6/6/2022 Approved OSVALDO PARAMO
Final 9/28/2022 OK to Issue CofO OSVALDO PARAMO
Green Building Final 9/28/2022 Approved OSVALDO PARAMO
MERV13>=Final 9/28/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Approved OSVALDO PARAMO