1935 S PURDUE AVE 90025
Certificate Information: 1935 S PURDUE AVE 90025
- Application / Permit
- 21014-10000-01350
- Plan Check / Job No.
- B21LA03616
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) HAB. ROOM OF AN (E) SFD TO A TWO-CAR GARAGE.
- Permit Issued
- Issued on 9/16/2021
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/19/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/23/2021 | JASON HEALEY |
| Applicant returned to address corrections | 7/2/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 7/28/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 8/11/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 8/25/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 9/16/2021 | MAHNAZ NOURHASHEMI |
| Issued | 9/16/2021 | APPLICANT |
| Building Plans Picked Up | 6/15/2023 | APPLICANT |
| CofO in Progress | 11/9/2023 | MICHAEL PELHAM |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
| CofO Issued | 11/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/1/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | MICHAEL PELHAM |
| Final | 11/9/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/9/2023 | Approved | MICHAEL PELHAM |
| Green Building Final | 11/9/2023 | Approved | MICHAEL PELHAM |
| Green Building Rough | 11/9/2023 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Approved | MICHAEL PELHAM |
| Smoke Detectors | 11/9/2023 | Approved | MICHAEL PELHAM |