1412 E 58TH ST 90011

Certificate Information: 1412 E 58TH ST 90011

Application / Permit
21014-10000-01348
Plan Check / Job No.
B21LA05168
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) CAR GARAGE INTO (N) ADU AND ADDITION
Permit Issued
Issued on 1/28/2022
Issuing Office
Current Status
CofO Issued on 4/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2021 APPLICANT
Assigned to Plan Check Engineer 3/24/2021 TSE MING HUANG
Corrections Issued 3/25/2021 TSE MING HUANG
Applicant returned to address corrections 3/25/2021 TSE MING HUANG
Applicant returned to address corrections 6/30/2021 CRISTINA SALAZAR
Applicant returned to address corrections 7/29/2021 TSE MING HUANG
Applicant returned to address corrections 9/5/2021 TSE MING HUANG
Building Plans Picked Up 10/26/2021 APPLICANT
Applicant returned to address corrections 1/18/2022 ZAW HAN
Plan Check Approved 1/20/2022 ZAW HAN
Issued 1/28/2022 APPLICANT
CofO in Progress 3/30/2023 BRENDAN MORELLI
Permit Finaled 4/3/2023 DEROLD HAUFF
CofO Issued 4/3/2023 DEROLD HAUFF
Permit Finaled 4/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/13/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 4/13/2021 THOMAS LANG
Sewer availability Cleared 5/4/2021 THOMAS LANG
Metro Rail approval Cleared 5/5/2021 TSE MING HUANG
CPC Cleared 5/7/2021 TERRI OSBORNE
Redevelopment Project Area Cleared 5/25/2021 GISELLE CORELLA
Eng Process Fee Ord 176,300 Cleared 5/26/2021 THOMAS LANG
Construction near power lines Cleared 6/3/2021 RIDWAN HARDY
Construction within easement Cleared 6/3/2021 RIDWAN HARDY
Hydrant and Access approval Cleared 6/11/2021 KURT CORRAL
Low Impact Development Cleared 11/24/2021 TA ANH

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Taewon; Lic. No.: C80632 2320 SANTA CRUZ CT      TORRANCE, CA 90501

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/19/2022 Approved JOAQUIN GREENOUGH
Pre-Inspection 6/3/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 6/13/2022 Partial Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 6/24/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/5/2022 Approved HORACE FULTZ
HVAC-Rough 9/2/2022 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 9/2/2022 Approved RYAN SALAZAR
Shower Pan 9/2/2022 Approved RYAN SALAZAR
Deputy Wood Construction 9/12/2022 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Rough 10/7/2022 Approved SHAVONNE ESPINOZA
HVAC-Rough 10/7/2022 Corrections Issued SHAVONNE ESPINOZA
HVAC-Rough 10/13/2022 Corrections Issued SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 10/28/2022 Conditional Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/2/2022 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 11/2/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/8/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 11/8/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/8/2022 Partial Approval ALIZAH MAYAGOITIA
Insulation 11/14/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 11/14/2022 Approved LILIANA PORTILLO
Drywall Nailing 11/28/2022 Approved JAMES CHAVEZ
ELECTRICAL-Final 3/7/2023 Approved BRENDAN MORELLI
Final 3/7/2023 Corrections Issued BRENDAN MORELLI
HVAC-Final 3/7/2023 Approved BRENDAN MORELLI
PLUMBING-Final 3/7/2023 Approved BRENDAN MORELLI
Final 3/29/2023 OK to Issue CofO BRENDAN MORELLI
Green Building Final 3/29/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 3/29/2023 Approved BRENDAN MORELLI