1412 E 58TH ST 90011
Certificate Information: 1412 E 58TH ST 90011
- Application / Permit
- 21014-10000-01348
- Plan Check / Job No.
- B21LA05168
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) CAR GARAGE INTO (N) ADU AND ADDITION
- Permit Issued
- Issued on 1/28/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | TSE MING HUANG |
| Corrections Issued | 3/25/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 3/25/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 6/30/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 7/29/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 9/5/2021 | TSE MING HUANG |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| Applicant returned to address corrections | 1/18/2022 | ZAW HAN |
| Plan Check Approved | 1/20/2022 | ZAW HAN |
| Issued | 1/28/2022 | APPLICANT |
| CofO in Progress | 3/30/2023 | BRENDAN MORELLI |
| Permit Finaled | 4/3/2023 | DEROLD HAUFF |
| CofO Issued | 4/3/2023 | DEROLD HAUFF |
| Permit Finaled | 4/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 4/13/2021 | THOMAS LANG |
| Sewer availability | Cleared | 5/4/2021 | THOMAS LANG |
| Metro Rail approval | Cleared | 5/5/2021 | TSE MING HUANG |
| CPC | Cleared | 5/7/2021 | TERRI OSBORNE |
| Redevelopment Project Area | Cleared | 5/25/2021 | GISELLE CORELLA |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | THOMAS LANG |
| Construction near power lines | Cleared | 6/3/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/3/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 6/11/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 11/24/2021 | TA ANH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 2320 SANTA CRUZ CT TORRANCE, CA 90501 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2022 | Approved | JOAQUIN GREENOUGH |
| Pre-Inspection | 6/3/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 6/13/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 6/24/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/5/2022 | Approved | HORACE FULTZ |
| HVAC-Rough | 9/2/2022 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 9/2/2022 | Approved | RYAN SALAZAR |
| Shower Pan | 9/2/2022 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 9/12/2022 | Conditional Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/7/2022 | Approved | SHAVONNE ESPINOZA |
| HVAC-Rough | 10/7/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Rough | 10/13/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| HVAC-Rough | 10/28/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/2/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/2/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/8/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/8/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 11/14/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/14/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 11/28/2022 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 3/7/2023 | Approved | BRENDAN MORELLI |
| Final | 3/7/2023 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 3/7/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 3/7/2023 | Approved | BRENDAN MORELLI |
| Final | 3/29/2023 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 3/29/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 3/29/2023 | Approved | BRENDAN MORELLI |